An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS Week LCLS Project Management Update M. Reichanadter / SLAC

  2. LCLS Performance – Aug05

  3. LCLS TEC Planned Spending / Month • LCLS currently spending and performing ~$3M/mo but planning at ~$5M/mo. • Leads to variances unless we can perform. • Is this a true work plan?

  4. LCLS Cost and Schedule Performance • Biggest SV (In, UN) appear to be due to an inaccurate plan not a schedule delay. • LCLS TEC in the Yellow in Aug05 (5 months after baseline) • Use the 6-mo look-ahead

  5. LCLS Cost and Schedule Performance • Biggest SV (In, UN) appear to be due to an inaccurate plan not a schedule delay. • LCLS TEC in the Yellow in Aug05 (5 months after baseline) • Use the 6-mo look-ahead

  6. Injector SPA Injector will be ~70% complete in Jan06

  7. Linac SPA Big spikes. Procurement payments? Are Managers planning a 6-month look-ahead? PMCS experts are at your disposal

  8. Undulator SPA

  9. LCLS Summary Schedule – Aug05 • Highlights • Schedule Float • Mar05 213 days • CP - Und B.O. - Und Inst to 1st Light • Sep05 - 177 days • CP - Und B.O. – Und Del - Und Inst to 1st Light • This needs to be fixed ASAP. • FY05 Shutdown • ~1 month • FY06 shutdown • ~ 4 months • FFTB Shutdown • Jul06 • LCLS may request advancing this date

  10. LCLS L1 – L2 Milestone Performance LCLS showing good milestone performance @ L2 in FY05

  11. LCLS L3 Milestone Performance – FY05 LCLS showing good milestone performance @ L3 in FY05

  12. LCLS L3 Milestone Performance – FY06 FY06 will be a key year for LCLS. Boost Phase

  13. Contingency Allocation to Date 77 BCR’s is high 5 months after baseline • CF: Interim work on CF + T2 increase, MMF and S20. CM/GC and 30% estimate overruns will require significant additional contingency. • UN: Undulator materials • Apr05 rebaseline covered schedule variances in Injector-Linac.

  14. LCLS Contingency Performance Contingency allocation has been reasonable to date. CM/GC + 30% CF estimate will make large draws on contingency in Oct05. Need to hold the line on contingency until Mar06 (CF construction bids).

  15. Richard M. BoyceDeputy to the Chief Engineer • Role/Responsibility; • Technical integration and coordination of LCLS deliverables; • includes space and logistics planning and coordination of deliverables to SLAC from its partner laboratories. • Serve as the Project Office point of contact for technical, integration and installation reviews for the LCLS project. Concur with System Manager’s review agenda, scope, minutes and/or any actions. • In close collaboration with the Quality Assurance Manager, the DCE will coordinate Engineering Specification Documentation and ensure that uniform standards are applied across the project. • Serve as a LCLS liaison to the SSRL division (other divisions?). • Member of the LCLS Project Office and Change Control Board. • Carrying out the LCLS Chief Engineer functions when the LCLS Chief Engineer is unavailable .

  16. LCLS Project Organization (Sep05)

  17. LCLS Staffing • 112.0 FTE’s (Sep05) • Staffing nearly complete • Still a few more to go • Does not include additional staff under contract • Jacobs • PMCS – AIM • Consultants • CM/GC (Oct05) FY05 funding @ SLAC Award Title I • Good News: LCLS has staffed up at the planned rate. • Are they all working on the right things? • SV says perhaps not Treading water. CR or full-funding?

  18. Davis – Bacon Approval Thanks to Richard M for working this issue!

  19. LCLS Technical Specifications Status • LCLS Specs • Jul05 • PRD’s @ 37% • ICD’s @ 5% • 67% is a big improvement but still more to go • ESD’s particularly IN, LN, and UN need more effort. • Physics support being added to Photon System

  20. Near-term LCLS challenges • LCLS is the execution phase of the project. Plans have been made, costs estimated, project approved … now it’s time to execute. • FY05-FY06 critical time (boost phase) of the project. Performance (solve problems, make decisions) is key. • Follow the P3 plan (Use the 6-month look ahead as a roadmap) • Less BCR’s and effort replanning your work each month. • Watch staffing levels (cost variances). Are the teams working on the plan? • Continue to document PRD’s, ICD’s ESD’s, & RDS’s. Mature design reduces risk. • Use the Risk Registry pro-actively to manage your work (not just a DOE requirement) • Prepare for start of LCLS Construction (CD-3b) • T2 CF is critical path for construction start • CM/GC on-board (Good news!) • PSAD will require effort from all groups • System Engineering and Integration • Start with ICD’s, PRD’s, ESD’s are the starting point • RMB and DM will maintain uniformity and high-quality across the LCLS • Need sustained effort on design reviews to mature design, track progress and identify integration issues. • Great Job so far! • MMF/S20/S24/FFTB under construction • Undulators under fabrication • Overall milestone performance is good • Shutdown going reasonably well so far • T2 >30%, CM/GC on-board • ISMS compliant. Be safe!