Logistic and Intermodal Transport in Serbia. Conference on Logistic Belgrade, 5 June 2012. 01-06-2011. Project. Task A : Market analysis and location selection ( 8 Working papers) – selection of location – traffic and market study
E N D
Logistic and Intermodal Transport in Serbia Conference on Logistic Belgrade, 5 June 2012 01-06-2011
Project Task A: Market analysis and location selection (8 Working papers) • – selection of location • – traffic and market study • Task B: Defining of the institutional framework and promoting the concept of terminal (7 Working papers) – institutional awareness • – terminal concept defined • – Workshops and Study tours • Task C: Preliminary design, feasibility studies and preparation of tender dossier (4 Working papers, Preliminary design and Tender dossier) • design documentation and tender dossier • economic and financial analysis
Traffic and market study • Envisaged routes: • 3 to 5 trains/week on relation with Rijeka (with antenna service to Koper) • 2 trains/week to Bar • 2 to 3 trains/week to Germany • 2 to 3 trains/week to Italy • 2 trains/week to Poland/Romania • 2 trains/week to Montenegro • 2 trains/week to Russia? 2-3 trains per day
Selection of location Stara Pazova Batajnica Pancevacki Rit Pancevo Zemun Surcin Ada Huja Dobanovci MCA… Makis Vrcin
Novi Sad Zemun
Terminal: I phase • 2 loading/unloadingtracks • truck loading lane • handling area • reach stacker • temporary storage area Loading tracks Reverse track 1010 m Outbound Inbound
Terminal: II phase • II b • 4 loading/unloading tracks • Gantry crane • “drive trough” terminal • II a • 4 loading/unloading tracks • gantry crane
Results of CBA • Basic case: 12 trains/week • The investment is no longer economically justified for 7 trains/week!
Results of financial analysis – Business plan • Income statement is positive from 2018 • 26 % ROE • EU donation is essential to achieve this result • Minimum number of trains for financial justification is 8 trains/week!
Functional structure • 2 functionally independent and separate entities are created under the public company structure • 22employees in Terminal Operator, 8 is Site Development Company
Future tasks • Preparation of urban planning documentation for construction • Application forIPA 2013 • Creation of future logistics platform • Attraction of logistic companies and investments • Creating of new jobs
Cooperation • MoIE and City of Belgradehave nominated Beoland as project investor • Preliminary design was submitted to Investor by Consultants • Investor will deal with all investor issues and land expropriation • EU/IPA financing, budget of RS and City of Belgrade • Framework and basic principles of cooperation for project implementation were defined • Creation of public company (Republic of Serbia and City of Belgrade)