1 / 17

Engineering school, Nancy, FRANCE 5 th and last year

Thibaut CARTIGNY. Guillaume PRADURAT. Engineering school, Nancy, FRANCE 5 th and last year. 1 year as ERASMUS students. Project about Transportation of natural gas from Hammerfest to Norrbotten and Northern Finland. Introduction. Semi-trailer. Pipeline. Melköya, Hammerfest 30 years.

aviva
Download Presentation

Engineering school, Nancy, FRANCE 5 th and last year

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Thibaut CARTIGNY Guillaume PRADURAT Engineering school, Nancy, FRANCE 5th and last year 1 year as ERASMUS students Project about Transportation of natural gas from Hammerfest to Norrbotten and Northern Finland CARTIGNY PRADURAT TEDELID

  2. Introduction Semi-trailer Pipeline Melköya, Hammerfest 30 years Train Ship CARTIGNY PRADURAT TEDELID

  3. Liquefaction Liquefying plant 2.5 G$ 1-15 Mtons LNG/ year 6TWh equivalent to 400 000tons CARTIGNY PRADURAT TEDELID

  4. Regasification • Warm the gas in a controlled environment • Either a big plant or small ones • Small plants: from 23 to 1500m3, from 400 000 to 10M$. • Big plant: from 100 000 to 1M m3, around 500M$. CARTIGNY PRADURAT TEDELID

  5. The total demand of LNG in Norrbotten and in the north part of Finland CARTIGNY PRADURAT TEDELID CARTIGNY PRADURAT TEDELID

  6. Transportation by semi-trailers • Size: 50 m3 of LNG per truck so 0.3GWh • 800km of road from Hammerfest to Kiruna or to Lulea • 1.5 hours for loading and same unloading • Cost: 440 000 $ • This option Needs: • 330 trucks at the same time for 6TWh per year!! • Many small re-gasification plant • But the cost doesn’t depend of the demand CARTIGNY PRADURAT TEDELID

  7. CARTIGNY PRADURAT TEDELID

  8. Transportation by trains • Size: 30 wagons per train, one wagon transports 110 m3 of LNG so 690MWh • 500km of railway between Narvik and Lulea • 2 travels per week per train maximum to distribute all destination so 2TWh per year • Cost: 135$/day/wagon • This option needs: • One ship between Hammerfest and Narvik • 3 trains for 6TWh • One tank per destination because the train can’t wait • Some trucks for the industries far from the railway • Many small re-gasification plants CARTIGNY PRADURAT TEDELID

  9. Transportation by ship • Size: between 40 000 and 200 000 cubic meter of LNG • 125 000 m3 of LNG represent 750GWh • 4000km from Hammerfest to Lulea so 1 week • For 6TWh we need 8 ships per year, one ship every 45 days • One ship consumes 1080 tons of gas per travel • Cost: 150 millions $ • This option needs: • One ship • One big terminal next to Lulea • A network of pipeline to distribute gas to each industry CARTIGNY PRADURAT TEDELID

  10. Transportation by pipeline • Pipes, compression stations, valves… • The gas is moved by the pressure gradient • The pressure is around 70bars • For 10TWh/year, we need a 8” main pipe • For 40TWh/year, we need a 16” main pipe • Power installed: 11MW for 10TWh, 50MW for 40TWh • Nearly no leakage, pipeline buried, very few accidents • No terrorism in Northern Scandinavia • Compressors driven by electrical motors • Compressors themselves environmentally friendly CARTIGNY PRADURAT TEDELID

  11. Pipelines planning CARTIGNY PRADURAT TEDELID

  12. Pipelines economy CARTIGNY PRADURAT TEDELID

  13. Comparison of the different options for a demand of 6TWh per year and without the costfor extraction of naturalgas CARTIGNY PRADURAT TEDELID

  14. Comparison of all options in function of the demand with a paying off investment in 10 years CARTIGNY PRADURAT TEDELID

  15. Comparison of all options in function of the demand with a paying off investment in 30 years CARTIGNY PRADURAT TEDELID

  16. Conclusion • Demand of roughly 6TWh per year at the moment • Either on environmental or economical point of views, the best way is to start with trucks until 1TWh, then to continue with pipelines • The size of the pipeline will depend on the demand for the next 30 years • Trains could be used until 8TWh during the construction of the pipeline • Ships are too expensive compared to the others CARTIGNY PRADURAT TEDELID

  17. Thanks for your attention ! CARTIGNY PRADURAT TEDELID

More Related