1 / 21

Primary beam production: progress - Extraction from LSS2 - Switching from TT20 at 100 GeV

Primary beam production: progress - Extraction from LSS2 - Switching from TT20 at 100 GeV. B.Goddard F.Velotti , A.Parfenova , R.Steerenberg , K.Cornelis , W.Bartmann, V.Kain, E.Carlier, A.Alekou , M.Meddahi, L.Jensen V.Mertens , Magdalena Kowalska

baba
Download Presentation

Primary beam production: progress - Extraction from LSS2 - Switching from TT20 at 100 GeV

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Primary beam production: progress- Extraction from LSS2- Switching from TT20 at 100 GeV B.Goddard F.Velotti, A.Parfenova, R.Steerenberg, K.Cornelis, • W.Bartmann, V.Kain, E.Carlier, A.Alekou, M.Meddahi, L.Jensen V.Mertens, Magdalena Kowalska A.Kosmicki, J.Osborne, I.Efthymiopoulos

  2. Extraction from LSS2 • Another test made on 3rd October with 100 GeV fast extraction, using MKP in LSS1. • Emittances of around 3.0 um (parasitic MD) • No losses in arc, even with ±10 mm bumps added at QFs • Next test planned 22nd October using LSS6 MKE kickers with 440 GeV beam • Cycle deployed, new working point tested, simulations made and settings defined

  3. LSS6 -> LSS2 at 440 GeVAntiphase bump through LSS1 New SPS working point with H tune of 26.87 for 2012 test (will eventually reuse Q_split to adjust this)

  4. LSS6 -> LSS2 at 440 GeVSimulation with aperture and envelopes 2.3 km

  5. LSS6->LSS2 at 440 GeVExtraction point More clearance than 100 GeV beam

  6. Switching from TT20:MBS magnets with open C-core 3.0 m magnetic length 1.65 T max field 70 mm H good field region

  7. MBS magnet cross-section 56 mm

  8. For TT20 switch • Only one spare 3.0 m MBS magnet exists • New series of ~10 probably required for AWAKE • For TT20 switch, need 3 new MBS magnets • 1.65 T field is possible (field quality not really any issue here) • Geometry already looks reasonable with ‘standard’ intermagnet drifts (for bellows and pumping ports)

  9. TT20 optics and geometry changes • Can manage by removing 1 MBE (211524) from the upper bending chain MBE.211524 removed

  10. Switch layout

  11. Switch detail Will probably need to reorganise layout of MDLV and BSGV to gain ~30 cm longitudinally – no major issue

  12. Impact of removing MBE dipole • Remove one vertical MBE dipole (8.4 mrad) • To arrive at same position in splitter for NA beams, need to trim strengths of remaining 12 dipoles in this bend (total k *13/12): • Option 1: arrange as 2+10 • One family at 74.1%, one family at 115.1% (2.096 T). New cabling and one by-pass convertor needed • Option 2: arrange as 6+6 • One family at 98.4%, one family at 118.3% (2.154 T). New cabling and 2 bypass convertors needed • Only Option 1 looks possible (MBE field maximum 2.1 T) • Unless reduce slightly beam energy for NA to keep same peak B as for SPS MBA/B (2.0475 T) • 2+10 then limits energy to 390 GeV • 6+6 then limits energy to 380 GeV

  13. TT20 Trajectory changeUp to ~80 mm vertical realignment neededover 120 m (larger for 2+10 split) 6+6 2+10

  14. Optics changes with new dipole layout Only visible in DY, and this negligible (advantage of keeping bend in same location) Beta functions Dispersion

  15. More Dy perturbation with 2+10 dipoles 2+10 6+6 2+10 6+6 2012 2012

  16. XY plane coordinates TT20 SBL

  17. Vertical coordinates With SBL switch, arrive in similar vertical plane as top of TT20 (vertical angle compensated by rolling slightly 2nd H bend family) TT20 SBL SBL TT20

  18. Junction considerations Splitters • A. Geometry with junction cavern • Beam angle about 130 mrad into new tunnel • Access possible between all tunnels (2 vacuum chambers to remove) • Long cavern (35 m)

  19. Junction considerations Splitters • B. Geometry with ‘core’ • Beam angle about 115 mrad at the tunnel wall • Access along TT20 blocked • Separate access needed for new SBL line

  20. Conclusions to date • 100 GeV LSS2 fast extraction tested: works with low intensity, large emittance. Still seems feasible. • 440 GeV to test next week from LSS6. • Switching from near top of TT20 looks possible at 100 GeV • We can use 3x MBS magnets (which need to be built) • May need to slightly rearrange MDLV corrector and BI • 1 MBE then needs to be removed from TT20 • Trajectory can be recovered without (significant) impact on optics • Needs 1(2) new power convertor(s) and recabling for remaining 12 magnets, into two new families • Vertical realignment needed of 120 m of TT20 • Other switch options/optimisations could also be possible • Coordinates for junction and start of SBL line defined • Options for cavern or parallel tunnel and core – transport?

  21. Next steps • Extraction from LSS2 • Beam tests on 23rd October for 440 GeV extraction (LSS6 -> LSS2) • Documentation of studies and MD results • Switch zone • Check of MBE maximum fields – 2.1 T may be OK, which points to 2+10 split and 400 GeV, but might need magnet tests at 6000 A. • Develop realistic junction civil engineering (cavern better for transport) • Iterate switch if needed to fit CE constraints • TT20 transfer line • Rematching of present TT20 optics to something more reasonable for low-loss beam transport • Checks of TT20 aperture with 100 GeV FT beam • Instrumentation inventory and upgrade requirements • New SBL transfer line • Finalisation of target coordinates needed! • Design of new 100 GeV line (new student just started working with ABT)

More Related