1 / 16

Stato elettronica UG controllo TRD

Stato elettronica UG controllo TRD. 26 Marzo 2008 A.Bartoloni, B.Borgia, F.Spada. UG-electronics in the TRD Gas System. QM design. Design of control electronics from EM to QM updated after test session in August 2004

bairn
Download Presentation

Stato elettronica UG controllo TRD

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Stato elettronica UG controllo TRD 26 Marzo 2008 A.Bartoloni, B.Borgia, F.Spada B.Borgia 26/3/2008

  2. UG-electronics in the TRD Gas System B.Borgia 26/3/2008

  3. QM design • Design of control electronics from EM to QM updated after test session in August 2004 • Contract issued to G&A Engineering for construction and qualification of QM and FM UG electronics  February 2005 • Radiation test of few components performed at Karlsruhe, under the supervision of Andrei Kounine, May 2005 • Further modifications were introduced because of gas circuit changes, e.g. 24V to 30V B.Borgia 26/3/2008

  4. Change power supply: 24V30V (supply for Kulite, Marotta valves, pumps, heaters) Pumps power supply: 12V directly from DC-DC converter, 24V with step-down circuit 30V24V. Heaters x CO2, Xe vessels: on/off switches identical to Marotta valves switches Added Kulite gauges Dallas T sensors replacing GP-50 T: + n. 2 dedicated links to USCM EM  QM No basic circuit was modified, i.e. ADC, switches, serial link QM FUNCTIONALITY TEST: JULY 2006 B.Borgia 26/3/2008

  5. Componenti • TIM January 2007: Siedenburgpresentò una lista di circa 15 componenti che secondo lui non erano approvati dalla collaborazione. • Di fatto un solo componente fu riconosciuto non accettabile. • Questo episodio ha scatenato una messa in mora, assolutamente non giustificata, della progettazione di Roma dell’elettronica UG. • E’ stata imposta una stretta supervisione di Aachen che ha richiesto l’approvazione formale di ogni passo nella progettazione e realizzazione della versione QM2. • In pratica la supervisione ha evitato due errori di layout ma ha ritardato notevolemente la realizzazione del QM2. B.Borgia 26/3/2008

  6. QM to QM2…….. • Following the change of linear regulators TPS73xx, of power distribution scheme and several changes required by safest operations (short circuits on cables or components), • we had to design new QM UGxx boards with following major modifications • replace the TPSxxxx regulators with SEL free LP2989 (UGBS, UGBC, UGFV) • put limiting resistor on Kulites and GP50 power supply lines (UGBS, UGBC) • separate 12V power supply for UGPS and flipper valve (UGFV) • introduce LP2953 regulator to generate 24V for pumps high speed (UGBP) • introduce LP2953 regulator to generate 21V for analog mux (UGBP) • eliminate 3.3V DC-DC converter; generate 3.3V from 5V on backplane • introduce Solid State Fuses (SSF) for short circuit protection on 5V, on each module • introduce pull-down resistors on Mosfet gates • introduce differential amplifier on Kulite inputs • eliminate UHVG (redesign of backplane) • eliminate 2 UGFV and reduce 8 multiple channels to 4 (redesign of pcb) B.Borgia 26/3/2008

  7. EPPCAN BUS POWER SUPPLIES A POWER SUPPLIES B ADC/DAC NATIONAL INSTRUMENT UG-electronics test set-up TV CHAMBER UG CRATE GAS SYSTEM SIMULATOR TEST STATION 29V 12V 5V B.Borgia 26/3/2008

  8. Test set up B.Borgia 26/3/2008

  9. B.Borgia 26/3/2008

  10. Vibration test B.Borgia 26/3/2008

  11. TVT B.Borgia 26/3/2008

  12. Qualification test command list Configuration file Time needed to perform all commands: 15 minutes B.Borgia 26/3/2008

  13. Stato UG • UGPS FM installati • UG-QM1 utilizzata sistematicamente per i test del TRD • Software UG usato per QM1 e per i test funzionali del QM2 • UG- QM2 test funzionali OK • Qualifica ESS e TVT del UG-QM2 inziata al SERMS il 13 Febbraio e terminata il 29 Febbraio con successo • 4 Marzo: UG-QM2al CERN per test funzionali con circuito di gas • 12 Marzo: UG-QM2 a Roma in attesa del UGPD B.Borgia 26/3/2008

  14. UG-QM2 • 14 Marzo: UGPD-QM arrivato a Roma • 18 Marzo: test funzionale UG-QM2+UGPD-QM ok • 25 Marzo: iniziotest EMC UG-QM2+UGPD-QM B.Borgia 26/3/2008

  15. UG-electronics schedule / QM2 • 21/01/08 QM2 boards ready • functional tests • 11/02/08 13/02 ready to start qualification tests (SERMS) • 29/02/08 29/02 end of qualification tests (no EMC) • 05/03 ready to start tests at CERN • 14/03/08 07/03 end of tests at CERN • 25/03/08 start EMC test • 27/03/08 end EMC test • Go ahead FM 2 weeks delay B.Borgia 26/3/2008

  16. UG-electronics schedule / FM • 04/04/08 FM boards delivered by G&A • Start acceptance tests @ SERMS • 21/04/08 end of FM boards acceptance tests • + 2 settimane di ritardo B.Borgia 26/3/2008

More Related