230 likes | 413 Views
DFW Connector Pavement Design and Construction Challenges and Solutions. 7 March 2014 2014 Virginia Concrete Paving Conference, Richmond, VA. By: Dan Dawood, P.E. DFW Connector. Owner: TxDOT D-B Firm: NorthGate Constructors Lead Design: PB Americas Pavement Design: Transtec
E N D
DFW ConnectorPavement Design and ConstructionChallenges and Solutions 7 March 20142014 Virginia Concrete Paving Conference, Richmond, VA By: Dan Dawood, P.E.
DFW Connector • Owner: TxDOT • D-B Firm: NorthGate Constructors • Lead Design: PB Americas • Pavement Design: Transtec • Cost: Over $1.0 billion • Publicly funded CDA: • $667 million from public gas taxes, • $250 million from ARRA funds, and • $107 million from bond proceeds for ROW acquisition. www.dfwconnector.com
DFW Connector • Project Length: 8.4-mile initial phase of 14.4-mile project, • Existing 12 Lanes Expanding to 24 lanes CL 2-3 lanes 6-7 lanes 2 lanes
Pavement Design Tasks • Thickness design • Reinforcement design • Temporary pavement design • Block-out solutions • Terminal joint design • Pavement transitions • Pavement widenings • Gore area design • Mix and materials • Resilient modulus verification
CRCP Thickness Design • PCC Thickness Design • 10” CRCP for Frontage Roads • 13” CRCP for Main lanes, Ramps, and Managed lanes • 2.5” HMA Base Layer • 12-36” Lime Stabilized Subgrade/Crushed Concrete Base (Effective Plasticity Index Requirements)
Reinforcement Design • Adopted updated reinforcement standard • CRCP (1) -03 • Longitudinal Steel • 13” CRCP: #6 bar @ 5.5” • 10” CRCP: #6 bar @ 7” • Transverse steel • Varies as a function of pavement width (PW) • For 13”: #6 @ 2.5’ for PW < 60 ft up to @1.0’ for PW < 120 ft, CRCP (1) -09 • Same Longitudinal Steel as CRCP (1) -03 • Transverse steel: #5 @ 48” for PW up to 100 ft
Optimized PCCP Mix • #57 stone, pea gravel, and natural sand
Other Pavement Design Tasks • CRCP Transition Design • CRCP to HMA • CRCP to existing CRCP • CRCP to new CRCP • CRCP Thickness Transition • Design of Pavement Widenings • Drainage Considerations • Remaining Life of Existing CRCP • Future Rehabilitation Needs • ProVAL Analysis - PI vs. IRI
Accelerated Construction Challenges and Solutions • Construction Schedule: 4 years (2010-2014) • Design-Build contracting process
Accelerated Construction Challenges and Solutions • Keep all lanes open during peak travel times • Temporary pavement to shift traffic
Accelerated Construction Challenges and Solutions • Keep all lanes open during peak travel times • Most lane closures scheduled to occur at night (off-peak)
Accelerated Construction Challenges and Solutions • Varying paving widths: • 12’ lanes, 10’-12’ shoulders, 16’-24’ ramps • 10’, 12’, 16’, 22’ and 24’ paving widths • 10”-13” paving thicknesses • Short poursdue to MOT and bridge construction EB & WB managed lanes – SH 114
Accelerated Construction Challenges and Solutions • Four new Guntert & Zimmerman pavers • S600 – 10’-18’ paving widths • S850 – 18’-24’ paving widths
Accelerated Construction Challenges and Solutions • Four new Guntert & Zimmerman pavers • Stringless compatible • Mobility – Tracks steer 90° • Telescoping End Sections • Easy to change widths – 2 hrs • 226 lane miles of CRCP (535,000 yd3)
Terex Batch Plant Model S • RexCon Dual Drum 12 yd3 plant • Capacity 600 yph. • Typical batch size is • 11 yd3 on flowboy rear discharge trailers • 7 yd3 on tandem dump trucks
Leica Stringless System North bound widening on SH121
Leica Stringless System Advantages: • Smoother ride • Eliminates man-hours in the field (production and safety). • Eliminates schedule impacts/coordination (stringline setup/removal). • Flexibility • Haul route • Trucks entrances and exits • jump around from area to area (easier set-up)