280 likes | 621 Views
Improved Techniques-Methods For Nuclear Power Plant Construction John Ioannidi, P.E. Bulatom, 2-4 June 2011. Introduction. Existing NPPs constructed using methods/technologies from 1970’s-1980’s Since then, new technologies utilized and lessons learned applied
E N D
Improved Techniques-Methods For Nuclear Power Plant Construction John Ioannidi, P.E. Bulatom, 2-4 June 2011
Introduction • Existing NPPs constructed using methods/technologies from 1970’s-1980’s • Since then, new technologies utilized and lessons learned applied • A number of methods sufficiently mature and proven to result in: • Proven Economic benefits • Reduced construction time (again, € savings) • New methods/technologies affect the following major activities: • Reinforced Concrete Placement • Concrete and Cement • High Strength Reinforcement • Modularization • Welding • Cold Bending
Comparison of Construction Schedules for Reinforced Concrete
Advances in Concrete and Cement • Improved Cement Powder Quality • Advanced Chemical Admixtures • Improved Mixing and Placement Techniques • Advanced Curing Techniques • Pozzolanic Admixtures • Development of Specialized Concrete Mix Designs
Self-Compacting Concrete (SCC) • New Reactor designs should take greater advantage of the benefits of advancing concrete technology… • Self Consolidating Concrete (SCC), also known as Self Compacting Concrete: highly flowable, can be placed in formwork with no vibration, minimal finishing. • SCC sets and cures in the same time as traditional vibrated concrete, but with much less labor. • The product flows around inside and throughout very congested formwork with little human intervention, greatly reducing the risk of honeycombing and voids.
Use of SCC • Mix Designs are Tested and Field Ready • Use is spreading globally • Benefits: Fewer Construction Workers • Reduces risk of injuries in field at any construction site • Reduces cost of project delays • Reduces probability of human error and negligence • Steel Structure Erection • Reduces overall cost of installation on large projects
Other Concrete Composition Technologies • High Performance Concrete (HPC) • Made with several different admixtures (super-plasicizer, fly-ash, silica fume) to achieve mix design properties • Must be properly mixed, transported, consolidate, cured • Provides higher compressive strength, density, and lower permeability) than traditional concrete Steel Structure Erection • Compressive strength: 101MPa (14.7ksi) – 131 MPa (19 ksi) versus 2.5 – 5 ksi. • Reactive Powder Concrete (RPC) • Capability for even higher compressive strengths than HPC (up to 200 MPa (29 ksi) • Produced by including metallic fibers in a dense cement matrix
High Strength Reinforcement • Steel is another basic building material that has undergone major improvements since the first generation of reinforcing steels applied to concrete. • Better Quality Control • Very Predictable Yield and Ultimate stress behavior • Improved Corrosion Resistance • Very wide range of sizes, shapes are available • Very high strength steels are being produced
Benefits of High Strength Reinforcement • Estimated that >200,000 m3 of Reinforced Concrete will typically be placed for a nuclear power plant • By replacing the larger diameter bars with smaller diameter bars of high-strength steel • Opportunity to reduce formwork congestion • Lower quantities of shipped and stored materials. • Reduced manual effort in field construction (lighter materials)
Prefabrication, Preassembly, Modularization • Module: remote assembly operations, prefabrication and preassembly. • Modules often the largest transportable unit or component of a facility. • Modules can be constructed remotely or constructed at the work site and then placed in position. • Equipment “skids” are an example of this technique used for a number of years by various industries
Modularization • Must be planned in the early design and procurement stages. • Increases engineering and procurement costs. • Net cost savings primarily results from shortened direct construction stage. • Is cost effective for critical or near critical schedule path work. • Benefits exponentially increase with each “N” plant. • Requires more integration of design discipline teams.
Positive Aspects of Modularization • Cost Savings – Time related, Quantity of field labor, Labor wage rate. • Significant schedule compression if properly designed and planned • Quality Improvement – Shop environment, “Out-of-hole” work. • Enhanced Worker Safety – Less Man-hours of exposure • More efficient placement of labor on the site to prevent equipment traffic congestion problems. • Higher utilization of specialized equipment and labor • Increased flexibility, even permitting remote (off site) construction of very complex or specialized modules, which can be transported to the site
Modularization Advantages • Onsite - assembly and modularization of equipment. • Offsite – Equipment manufacturers provide a complete and assembled component skid to the jobsite • Packaged - All equipment is provided to a central facility for assembly and installation in modules. These modules tend to be of a massive size and require very specialized transportation equipment and coordination.
Modularization Advantages • Reduced time Related Fixed Costs • Construction Management • Construction Facilities/Utilities • Construction Equipment • Reduce Overall Project Cost • Total Project Cost – 10%, more for “N” Plants. • Onsite Labor 25% • Construction Risk and Mitigation Cost • Project Funding Interest • Reduced Schedule Duration • Sequential to Parallel Activities • Shop Environment Productivity • Site Weather Impacts • Increased Productivity and Quality • Shop Labor Environment & Skill • Shop Advance Tool Use • Out-of-hole Site Work • Reduced Site Manpower Density • Ground Level Work • Increased Productivity • Reduced Safety Risk
Modularization Disadvantages • More Transportation Cost • Double Shipment – Manufacturer/Module/Site • Wider, Longer, Heavier Loads • Special Handling • Added Risk for Transportation Damage • More Construction Equipment Cost • Special Cranes – Very Heavy Lift • Larger Capacity • Added Engineering Cost – 10 to15% • More Detail Required • More Intra-Discipline Planning • Earlier Design Availability Risk • More Procurement Cost – 17 to 20% • Added In-shop Work • More Coordination and Administration • More Sacrificial Material • Increase Cost & Schedule Risk if Late Delivery
Open-Top Installation • Capacity of cranes increased (up to 900 tons) • Can Shorten construction schedule • Reduce construction costs (direct and indirect)
High Deposition Rate Welding • Welding processes used in nuclear plant construction include: • Structural welds to connect structural members • Pressure welds • Weld cladding (deposition of weld metal on surface of other metal to improve characteristics) • Quality welding, crucial to construction of nuclear plant, is time consuming • Deposition of metal at higher rates without compromising quality is desired and make a significant contribution to reducing construction times.
High Deposition Rates Welding Methods • Gas Metal Arc Welding • Gas Tungsten Arc Welding • Submerged Arc Welding • Robotic Welding (Can be used with most type of welding Process): • Gas metal arc welding (GMAW) • Gas tungsten arc welding (GTAW) • Flux core are welding (FCAW) • Submerged arc welding (SAW) • Robotic Welding most suited for shop work (Controlled environment and repeated)
3D Modeling Highlights • 3D Modeling can be used at all stages: conceptual, detail engineering/design, construction, O&M • Construction rework labor typically can cost as much as 12% of total construction labor using manual method of design Submerged Arc Welding • 3D allows better: • Visualization • Early automated interference identification and resolution flux core are welding (FCAW) • Work planning and sequencing • Result of above is reduction of rework labor to ~ 2%
Pipe Bends Vs. Welded Elbows • Pipe bending is a simple alternative construction technique to: • Speed up piping system construction • Reduce the number of workers required • Pipe bending technology previously available, but at that time, welded-in fittings were more cost-effective • Pipe bending may now be performed at a lower cost than welding. • Development of portable bending machines allows on-site bending of pipe.
Bending Techniques • Cold Bending • Heat not applied to pipe to reshape pipe • Types of cold bending
Bending Techniques • Heat Induction Bending • Hot Slab bending • Whichever method or combination of methods used, appropriately used, process could results in time and money savings.
In Summary • New Approaches, Materials, and Methods available today that can help reduce the risk associated with mega project construction. • Early planning, engineering and design involvement, and aggressive management will promote use of technological innovations. • Higher costs in some areas of innovations are usually compensated for in Labor and/or Schedule savings • Implementing improved construction techniques provides a much more secure environment for those financing a project, with on-time production of energy to the public/private consumer as a critical benefit to stakeholders.