Taesang Choi choits@etri.re.kr CJK NGN Test-bed Proposal by TTA
Contents • Testing Call Server Architecture • Testing Network Architecture • Test Scenarios and Items • Testing Schedule Proposal
ETRI’s CS Architecture Back-End Servers Application Server External IP Network MS/IVR 3rd Party Application Server SIP OSA/Parlay BSS NMS SCP SIP MGCP H.248/Megaco Diameter RADIUS Proprietary SIP Network OSA/Parlay Gateway SNMP FTP or Proprietary SIP(-T) SIP Server INAP Softswitch SS7 ISUP/TCAP/SCCP AIN INAP SIP(-T) STP Sigtran(SCTP/M3UA) SSW Network SIP-T H.323 BICC* SSW SG SS7 MGCP H.248/Megaco H.323 Network SBC H.323 GK Server TG SIP(-T),H.323 TDM (ISUP) SIP H.323 MGCP H.248/Megaco* Circuit Switch IP-PBX GK Residential Access AG / RG Enterprise Access
Testing Network Architecture • APII Testbed • Korean Side • Name: KOREN • NOC: KIX in NCA • Connectivity: • POS OC3: 155 Mbps to China • 2 x 1Gbps Ethernet to Japan • China/Japan Side • TBD • Type • IPv4/IPv6 network • No MPLS & other QoS functionality available yet • TBD • Need investigation on MPLS/QoS support • Current link capacity may not be enough
Signaling Link Bearer Link ETRI’s CS Lab Network Configuration Japan CERNET 155M POS Internet Border Router 2G Ethernet Support Facility GBE Management/ Monitoring System, GW, SIP phones, … GBE, 100BT, 10BT Meeting Room 100BT SBC 100BT(VLAN) L2 스위치 100BT 100BT 100BT 100BT 100BT AS/MS CS SG/TG RACF Packet Monitor E1 TDM 100BT PSTN 모델망
Test Scenarios and Items • Target Test Scenarios • VoIP Interworking • PES/PSS Interworking • VoIP Performance Evaluation • PES/PSS Performance Evaluation • VOIP/PES/PSS Interworking with RACF Involvement • Testing Items • Basic Functionality Testing cases • Call Setup • E2E Call Setup Delay • Call Completion Rate • Each Segment IPTD/IPDV/IPLR/Path unavailability • Call Traffic Accounting • Harmonization Testing ofService QoS class differences among CJK • Equipment Related Testing cases • Various User Terminal Testing • Network Related Testing cases • IP address allocation • Network connectivity setup • Etc.
Testing Schedule Proposal • Phase I: 2006 3rd/4th Quarter • Network Connectivity • VoIP Testing • VoIP Performance Evaluation • First Report/Demo during 8th CJK NGN Meeting (2006 Nov or Dec) • Phase II: 2007 1st/2nd Quarter • PES/PSS Interworking • PES/PSS Performance Evaluation • Second Report/Demo during 10th CJK NGN Meeting (2007 July or Aug) • Phase III: 2007 3rd/4th ~ 2008 1st/2nd Quarter • VoIP/PES/PSS Interworking with RACF involvement • Performance Evaluation for VoIP/PES/PSS Interworking with RACF involvement • Third Report/Demo (2008 July or Aug)