Information for Meeting in Sweden. Feedback from uk national agency. Management and Monitoring. Broadly on schedule – must avoid further slippage More hands on management from UK (Decide how October 2010 ) stronger communication closer more regular monitoring
E N D
Management and Monitoring • Broadly on schedule – must avoid further slippage • More hands on management from UK (Decide how October 2010) • stronger communication • closer more regular monitoring • Concrete deadlines and milestones • Interim report information from partners (October 2010) • Use interim Report to emphasise benefits and highlight achievements (October 2010)
WP3 and WP4 • 31 October deadline for all products for “preparation and transfer of materials” • Decision to transfer production of methodologies for teachers from WP4 to WP3 to be explained (Done) • Explain which materials are to be translated (October 2010) • Clarify timeline for testing materials (October 2010)
Budget changes • Now approved
Partner Monitoring • To introduce quarterly monitoring reports linked to finance and timesheets (Agree format October 2010, submit 15 January 2011 for October to December)
Quality Assurance • Recommends producing quarterly quality assurance reports (Due January 2011) • Self assessment for partnership • Highlights • Lowlights • Opportunities for improvement
Communication • Recommends an additional partnership meeting to support piloting (Decision October 2010) • Or bilateral meetings • Must be within existing costs • Must prioritise regular and high volume communication in second half of project
Impact • What indicators will we use to measure success? (October 2010) • What statistics will we gather? (October 2010) • Define realistic indicators per country by Interim Report (consult application form) (October 2010)
Sustainability • All partners to start putting into place formal arrangements for using products after the project has finished
Finance • Carol must have copies of timesheets with signatures (Immediate) • Simple translation required on invoices (Immediate)
Dissemination • All partners to report in more detail on dissemination activities (October 2010) • Common template to be produced to record on a regular basis (October 2010) • Dissemination to be a key feature of second year of project
Website • All online resources to be linked to website by December 2010 • Clear signposting to Angus College website • Website structure to consider needs of target groups • Clear mapping and signposting • Step by step guide to be considered (December 2010)
What is required from partners? • Interim report pages sent by email • Draft responses in groups (by WPs and national groups?)
Evaluation and reporting • What is your opinion of our method for evaluating meetings? • What else should we report on? • How should we report?