1 / 23

PAR 1085 – SOUTH SECONDARY IMPROVEMENTS PROJECT A 4D GIANT

PAR 1085 – SOUTH SECONDARY IMPROVEMENTS PROJECT A 4D GIANT. Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012. Outline. PAR 1085 South Secondary Improvements Project What is 4D ? Building the 4D Model 4D Visualization The Benefits Summary

bayard
Download Presentation

PAR 1085 – SOUTH SECONDARY IMPROVEMENTS PROJECT A 4D GIANT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PAR 1085 – SOUTH SECONDARY IMPROVEMENTS PROJECTA 4D GIANT Eric M. Wetzel Carollo Engineers, Inc. Bentley Be Inspired Awards November 13, 2012

  2. Outline • PAR 1085 South Secondary Improvements Project • What is 4D? • Building the 4D Model • 4D Visualization • The Benefits • Summary • Questions South Secondary Improvements Project

  3. South Secondary Improvements Project Metro Wastewater Reclamation District Robert W. Hite Treatment Facility (The District)

  4. South Secondary Improvements Project • $136 million w/ potential $1.8 million bonus for early completion • Meets new wastewater discharge criteria and adds capacity • Very tight schedule to meet permit compliance

  5. Carollo Engineers’ Role • Design Engineer & Owner’s Representative during construction • Review Contractor’s construction schedule to verify compliance with the Contract • Responsible for 3D and 4D models

  6. South Secondary Improvements Project What is 4D?

  7. What is 4D? • 4D is a tool that links a 3D CAD model with a construction schedule • The resulting 4D model allows visualization of the planned construction sequence 3D Model + Schedule = 4D Visualization

  8. South Secondary Improvements Project Building the 4D Model

  9. 3D Model • Software Used • Bentley MicrostationV8XM • Bentley Architecture V8XM • Bentley Structural V8XM • PlantSpace Design Series V8XM • InRoads XM • ProjectWise V8i • ProjectWise InterPlot • Navigator V8i • 65 Total Models • Anything above 2” pipe was modeled • 99 Reference Files • Completed during the design phase • Finalist – Be Inspired Awards 2011

  10. 3D Model Elements • To achieve a 4D visualization, the 3D model must be designed into constructible elements • Construction Joints • Pipe Joints • 3D model must match the depth of the construction schedule

  11. Construction Schedule Structural Drawings vs. Construction Schedule • Software: Primavera P6v7.0 • Extremely detailed consisting of 12,143 activities

  12. Linking the Model and Schedule • Import accepted Primavera P6 Schedule into Bentley Navigator V8i • Link activities in Schedule to Item Sets in the Model • Drop and Drag • After Linking is complete: • Close Navigator V8i and Open linked model in Microstation • Use Animation Producer in Microstation to create image frames • Set time frame (May ‘11 – June ‘13) • Set frame duration (daily, weekly, etc.) • Import frames to Camtasia for .AVI development

  13. Visualizing the Visualization • While watching the 4D visualization • Every start activity will turn the item set within the model green • Every finish activity will turn it to the model color. Yellow in this example • Example: Concrete – Rebar, Form, Pour, Cure

  14. PAR 1085 South Secondary Improvements Project 4D Model – South West Blower Building

  15. South Secondary Improvements Project The Benefits How does this help?

  16. 4D Benefits • Tool for Risk Mitigation • 4D analysis validated Contractor’s realistic ability to obtain full bonus ($1.8 million) • Detailed review and identification of issues in the schedule

  17. Example 1: Concrete Pour Sequence Compliance Schedule Bust: Wall and Slab are poured concurrently. A single bust = Potentially 14 calendar days. Schedule Bust: Wall is being poured prior to Slab

  18. Example 2: Missing Activities/Links or Inappropriate Logic “A” – Schedule did not reflect updated CJs. “B” – Threshold of two facilities. Not accounted for in schedule Missing Activities/Links Upon completion of linking the schedule to the model, linked items can be turned off to show only model items not linked to an activity B A

  19. Example 3: Visual Assessment of Actual vs. Planned 10/2/2012

  20. 4D Benefits – Cont. • An updated 3D model for Owner’s use • Public Outreach • Identification of non-conformance with Contract • Ability to look-ahead and plan for future Work activities

  21. South Secondary Improvements Project Summary

  22. Summary • 4D tool mitigated significant risk associated with a complex and accelerated schedule • Minimize logic loops, missing activities, non-conformance, etc, to account & save significant time in the schedule. • Estimated at 60 working days to date • A tool to engage stakeholders without a tangible connection to the project • An updated 3D model that can be used for facility maintenance or modifications • Versatile Bentley software was utilized in all facets of 3D and 4D development • No hardware or software costs incurred to produce 4D

  23. Questions? Eric M. Wetzel, LEED-AP BD+C Project Controls Carollo Engineers, Inc. 390 Interlocken Crescent, Broomfield, CO 80021 (303) 286-3047

More Related