1 / 20

By: Prof. Y. Peter Chiu

MRP & JIT ~ HOMEWORK SOLUTION ~. By: Prof. Y. Peter Chiu. #4 (a) MPS for the computers. . . . #5. #6. # 9. (b). Week. 27 28 29 30 31 32 33 34 35. MPS-end item. 165 180 300 220 200 240. Component B (P.O.R).

Download Presentation

By: Prof. Y. Peter Chiu

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MRP & JIT ~ HOMEWORK SOLUTION ~ By: Prof. Y. Peter Chiu

  2. #4(a) MPS for the computers   

  3. #5

  4. #6

  5. # 9 (b) Week 27 28 29 30 31 32 33 34 35 MPS-end item 165 180 300 220 200 240 Component B (P.O.R) 330 360 600 440 400 480 Component F 330 360 600 440 400 480 -Net. Req. Time Phased Net. Req. 330 360 600 440 400 480 Ans. →Planned Order Release 330 360 600 440 400 480

  6. # 9 (c) Week 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 165 180 300 220 200 240 MPS-end item P.O.R –Comp. B 330 360 600 440 400 480 330 360 600 440 400 480 Net Req. –Comp. E 330 360 600 440 400 480 Time Phased –Net Req. P.O.R – Comp. E 330 360 600 440 400 480 660 720 1200 880 800 960 Net Req. –Comp. G 660 720 1200 880 800 960 Time Phased –Net Req. P.O.R –Comp. G 660 720 1200 880 800 960 660 720 1200 880 800 960 Net Req. –Comp. I 660 720 1200 880 800 960 Time Phased –Net Req. Ans. → P.O.R –Comp. I 660 720 1200 880 800 960 (d) 1980 2160 3600 2640 2400 2880 Net Req. –Comp. H Time Phased –Net Req. 1980 2160 36002640 2400 2880 Ans. → P.O.R –comp. H 1980 2160 36002640 2400 2880

  7. # 14 Month 1 2 3 4 5 6 7 8 9 10 11 12 Demand 6 12 4 8 15 25 20 5 10 20 5 12 • Current Inventory : 4 • An ending Inventory should be : 8 • h = $ 1 • k = $ 40 Month 1 2 3 4 5 6 7 8 9 10 11 12 Net. Demand 212 4 8 15 25 20 5 10 20 5 20 (a) Silver-Meal • Starting in Period 1 : C(1) = 40 C(2) = (40+12)/2 = 26 C(3) = [40+12+2(4)] /3 = 20 C(4) = [40+12+2(4)+3(8)] /4= 21 <stop> ∴

  8. # 14 (a) Silver-Meal C(1) = 40 C(2) = [40+15]/2 = 27.5 C(3) = [40+15+2(25)] /3 = 35 <stop> • Starting in Period 4 : ∴ • Starting in Period 6 : C(1) = 40 C(2) = [40+20]/2 = 30 C(3) = [40+20+2(5)] /3 = 23.3 C(4) = [40+20+2(5)+3(10)] /4 = 25 <stop> ∴ • Starting in Period 9 : C(1) = 40 C(2) = [40+20]/2 = 30 C(3) = [40+20+2(5)] /3 =23.3 C(4) = [40+20+2(5)+3(20)] /4 = 32.5 <stop> ∴ ∴ ∴ Using Silver- Meal ; y = [ 18 , 0 , 0 , 23 , 0 , 50 , 0 , 0 , 35 , 0 , 0 , 20 ]

  9. # 14 (b) LUC • Starting in Period 1 : C(1) = 40 /2 = 20 C(2) = 52 /14 = 3.71 C(3) = 60 /18 = 3.33 C(4) = 84 /26 = 3.23 C(5) = (84+60) /41 = 3.51 <stop> ∴ • Starting in Period 5 : C(1) = 40 /15 = 2.67 C(2) = 65 /40 = 1.63 C(3) = [65+2(20)] /60 = 1.75 <stop> ∴ • Starting in Period 7 : C(1) = 40 /20 = 2 C(2) = (40+5) /25 = 1.80 C(3) = [40+5+2(10)] /35 = 1.86 <stop> ∴

  10. # 14 (b) LUC • Starting in Period 9 : C(1) = 40 /10 = 4 C(2) = 60 /30 = 2 C(3) = [60+2(5)] /35 = 2 C(4) = [70+60] /55 = 2.36 <stop> ∴ ∴ ∴ Using LUC ; y = [ 26 , 0 , 0 , 0 ,40 , 0 , 25 , 0 , 35 , 0 , 0 , 20 ] (C) PPB Period Holding cost • Starting in Period 1 : 1* (12) = 12 12+2(4) = 20 20+3(8) = 44 2 3 4 K = $40 Closer to period 4 ∴

  11. (C) PPB Period Holding cost • Starting in Period 5 : 1 2 3 0 25 25+2(20) = 65 K = $40 Closer to period 2 ∴ Period Holding cost • Starting in Period 7 : 2 3 4 5 5+2(10) = 25 25+3(20) = 85 K = $40 ∴ Closer to period 3 Period Holding cost • Starting in Period 10 : 2 3 5 5+2(12) = 29 K = $40 ∴ ∴ Using PPB ; y = [ 26 , 0 , 0 , 0 ,40 , 0 , 35 , 0 , 0 , 45 , 0 , 0 ]

  12. # 14 (d) 1 2 3 4 5 6 7 8 9 10 11 12 SM 18 0 0 23 0 50 0 0 35 0 0 20 LUC 26 0 0 0 40 0 25 0 35 0 0 20 PPB 26 0 0 0 40 0 35 0 0 45 0 0 Demand 2 12 4 8 15 25 20 5 10 20 5 20 Inv. SM Σ = 95 16 4 0 15 0 25 5 0 25 5 0 0 24 12 8 0 25 0 5 0 25 5 0 0 Inv. LUC Σ = 104 Inv. PPB 24 12 8 0 25 0 15 10 0 25 20 0 Σ = 139 Cost of S.M. ($40*5)+($1*95) = $295 Cost of LUC ($40*5)+($1*104) = $304 Cost of PPB ($40*4)+($1*139) = $299 ∴ Silver Meal Method is the least expensive one !

  13. K=200; h=0.3 #17

  14. #17

  15. #17

  16. #18

  17. #18 (cont’d)

  18. # 24 • h = $0.4 • Starting Inventory Week 6 is 75 • K = $180 • Receiving: 30 & 10 in week 8 & 10 Week 6 7 8 9 10 11 Demand 220 165 180 120 75 300 Net Demand 145 165 150 120 65 300 (a) PPB : Holding costs Week • Starting in Period 1 : 1 2 3 0 165*0.4= 66 66+2(0.4)(150)= 186 K = $180 Closer to period 3 ∴ Holding costs • Starting in Period 4 : Period K = $180 1 2 3 0 65*0.4= 26 26+2(300)(0.4)= 266 Closer to period 3 ∴

  19. # 24 MRP - Mother Boards Week 1 2 3 4 5 6 7 8 9 10 11 Net. Req. 145 165 150 120 65 300 Time-Phased Net Req. P.O.R. (lot-for-lot) 145 165 150 120 65 300 145 165 150 120 65 300 Ans. →( PPB ) P.O.R 460 0 0 485 0 0 For DRAM Ans. →Gross Req. 41,400 0 0 43,650 0 0 For DRAM Time-Phased Net Req. 41,400 0 0 43,650 0 0 For DRAM P.O.R. 41,400 0 0 43,650 0 0

  20. The End