nQPS commissioning

nQPS commissioning. …a long way to go. Topics. nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary. nQPS system - components. Cable connections. Signals BS/DS. Interlocks. Heaters. Power. FIP. In numbers: 450x DQLPU 450x DQAMGs

belden
Download Presentation

nQPS commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. nQPS commissioning …a long way to go

  2. Topics • nQPS component overview • Enhancements in Firmware • Commissioning diagram • Detailed task list • Summary

  3. nQPS system - components Cable connections Signals BS/DS Interlocks Heaters Power FIP In numbers: 450x DQLPU450x DQAMGs 1700x DQQDS 2100x DQQBS DQLPU DQQBS 3x DQQDS2x DQQBS 2x DQQDS2x D Q A M G S Crate Crate controller Bad splice detection board Symmetric quench detection board

  4. nQPS enhancements • New Firmware for DQAMGS and DQQDS boards • DQAMGS: Better diagnostics/stability (automated sector set-up possible) • DQQDS: new logic prevents chain reactions and protects against single negative pulses • DQQDS: Enhanced buffer functionality • DQQDS: Adaptive filter onset programmable • DQQBS: New threshold (500uV)

  5. ELQA finished, signal cables connected Po phase 0 Bring up “old” QPS system (FIP/Power/Interlocks) nQPS basic tests (test cabling by heater firing set BS coefficients & threshold) nQPS advanced tests up to 2kA(pyramids, fast power abort @2kA, BS coefficients fine tuning) Po phase 2 Connect nQPS to interlocks Test of interlocks Po phase 2 (phase 0 possible) Connect nQPS to heaters Heater firing from nQPS, Final nQPS tests: Pyramids up to 5kA, energy extractions up to 6kA) Po phase 2

  6. nQPS HWC Powering Phase 0 • DQLPU, TUNNEL: Re-connection of the signal/power cable • DQQDS, TUNNEL: Firmware upgrade for DQQDS boards. All 4 cards will be exchanged by updated ones. Update of equipment database • DQAMGS, TUNNEL: Firmware upgrade for DQAMGS crate controllers (exchange of boards) • TUNNEL: Re-powering of the 110 Power-Packs of the sector • TUNNEL: Re-establish FIP communication with all nQPS controllers of the three main circuits in the arc to be commissioned. • DQHDS, CCC: Test of the ‘old QPS’ interlocks. Close interlock loop.Time: 2h/sector • DQHDS, TUNNEL: Re-powering of the DQHDS in the arcs and in the LSS’. Verification of correct charging. • DQQBS/DQQDS, CCC: Check of all picked-up voltage signals (noise floor) on BS and DS boards. Ramp to 110A to see if all cards are alive.Time: 2-8h/sector • DQQBS, CCC: Using the new write/read tool: Load a default set of Inductive Compensation Coefficients. Read back the values and compare. Time: 3h/sector

  7. nQPS HWC Powering Phase 2 (1/3) • DQQBS, CCC: Ramp to inj. current and dump. Calculate and correct the compensation values. Ramp again for verification. To be repeated until satisfaction. Time: 8h min./sector • DQQBS/DQQDS, CCC: Fire heaters in groups from “old” QPS. Signatures recorded by BS and DS boards to be used to verify cabling/configuration/HDS controller position. Verification of proper heater discharge curves. (PM)Eventually pre-cycling to 110A or 350A required. (PO Phase 0 possible) Time: 2h/sector + 2-4 hours off-line • DQQBS/DQQDS, CCC: nQPS interlock checking. Verification of correct operation of the interlock chain. Ending with ramp to 2 kA to confirm operation without trigger activation (with interlock still disabled)Time: 2 – 4h/sector • DQQDS, CCC: Type test in the first commissioned sector: Opening of the EE facilities at ~ 1000A during an upwards ramp.Time: 2h • DQQBS/DQQDS, TUNNEL: Interconnection of the nQPS to the Interlock Chain. Time: 4 h/sector

  8. nQPS HWC Powering Phase 2 (2/3) • DQQBS/DQQDS, CCC: Test of nQPS interlocksTime: 2h/sector (PO Phase 0 possible) • DQQBS/DQQDS, CCC: Repetition of ramping test to 2 kA. Energy Extraction from 2 kA. Time: 4h/sector • DQQBS, CCC: Perform a Measurement Pyramid (Splice Monitor) to 2 kA, mainly to verify the repaired cabling (PI2.s1). Time: 3 – 4h/sector • DQQDS, TUNNEL: Interlinking the heater firing circuits of the nQPS (connecting the nQPS with the heaters)Time: 2h/sector. • DQQDS, CCC:Heater firing test from nQPS – in groups. Off-line analysis Time: 2h/sector + 2-4h analysis (PO Phase 0 possible)

  9. nQPS HWC Powering Phase 2 (3/3) • DQQDS, CCC:Ramp to 4 kA. Energy Extraction at 4 kA. Analyze the results. Time: 2h/sector, analyzing 4h/sector • DQQBS, CCC: Perform a Pyramid to 5 kA. Analyze the results. Time: 4h/sector • DQQBS, CCC: Ramp in two steps to 6 kA. Analyze the results. Calorimetric measurement by CRG Time: 8h/sector, incl. preparation time • DQQDS, CCC:Ramp to 6 kA. Energy Extraction at 6 kA. Analyze the results. Time: 4 hours • DONE, nQPS fully commissioned for 3.5TeV operation…

  10. Summary • Re-commissioning of the nQPS system after connector repair(almost all tests of nov/dec have to be repeated (S12) or done the first time) • Firmware updates for enhanced functionality/stability • New threshold value for the DQQBS (500uV allows smoother operation due to more margin) • Commissioning time in CCC estimated to ~65h per sector (tunnel interventions not included)