An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TGP OutagesAugust & September 2013 Customer Webex July 25th, 2013

  2. Agenda • Review of Upcoming Outages • August & September • Q&A

  3. Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Tennessee Gas Pipeline tariff to mean a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m. (Central Clock Time).

  4. Disclaimers • Scheduled dates are subject to change. • Projects may be added, altered, delayed or cancelled. • TGP will provide notice of such additions or changes via PASSKEY postings. • Dates as posted on PASSKEY should be deemed correct in the event of conflicts between PASSKEY posted dates and dates within this presentation.

  5. Color Key for Maps • Green • No Impact Anticipated • Yellow • Restrictions are possible, but not likely • With extended duration, restrictions could be necessary from time to time • (M) denotes that meter(s) may be impacted, refer to EBB posting • Red • Restrictions are probable

  6. Div 5 & 6 –August Outages Hydrotest 40-3 to 41-3 (7/8/2013-8/27/2013) ILI Pigging MLV 823-1 to 827-1 (8/6/2013)(M) Class change 511-1 to 512-1 (7/15/2013-8/7/2013) Hot Tap (M) 8-1 to 9-1 (7/26/2013-7/27/2013) ILI Pigging 4-3 to 9-3S (8/6/2013-8/8/2013) Cleaning Pig 409A-1101 to 409A-1102 (8/20/2013-8/21/2013) Unit Maintenance Sta. 409A (8/14/2013-8/21/2013) ESD Test Sta. 409 ESD (8/6/2013-8/7/2013) Sta. 409A ESD (8/8/2013-8/9/2013

  7. 2013 Outages – Offshore Outages Sta. 523 - Station & Line Tie-ins (7/24/2013-8/10/2013)(M) Sta. 523 (36") Line outage - SAM Sale Outage (6/22/2013-8/10/2013)(M) 507F-100 (Grand Chenier) -- SAM Sale Outage (7/22/2013-7/31/2013) (M) Sta 523 – Unit Outage (4/11/2013-8/10/2013)

  8. Div 8 & 9 – August Outages Hydrotest109-3 to 110-3 (6/15/2013-8/15/2013) Rosehill Class Change 558 to 860 (Line 2 & 3) (7/15/2013-11/1/2013) Anomaly Remediation 72-1 to 77-1A (7/8/2013-8/16/2013) Bi-Directional Operation Sta 555 (5/29/2013-8/13/2013) Station MaintenanceSta. 843 (8/30/2013) Purchase Power Upgrade Sta. 834 (7/15/2013-7/29/2013) Station MaintenanceSta. 834 (8/7/2013)

  9. Div 10(200 Line) – August Outages Anomaly Remediation 200-4 to 219-4 (11/16/2011-12/31/2013) 205-2 to 206-2 (8/15/2012-10/31/2013) 207-2 to 208-2(8/15/2013-10/31/2013) 208-2 to 209-2 (3/7/2012-8/15/2013) Station 219 Maintenance ESD (8/15/2013) Pipe Replacement MLV 204-4 (8/5/2013-10/11/2013) MLV 212-4(8/5/2013-10/11/2013) Hydrotest MLV 200-1A to 201-1 (7/18/2013-9/4/2013) MLV 203-1 to 204-1 (8/5/2013-10/11/2013) MLV 208-3 to 212-3 (8/2/2013-12/19/2013) 213-3 to 214-3 (8/5/2013-10/11/2013)

  10. Div 10(200 Line) – August Outages Station Maintenance Sta 267 (8/27/2013-8/28/2013) Unit Maintenance Sta 266A (8/13/2013-8/16/2013) Sta 266A (8/19/2013-8/23/2013) Anomaly Remediation 268A-101.1 to 268A-103 (Fitchburg) (7/15/2013-8/16/2013) 267-1 to 270C-101 (Beverly Salem) (8/12/2013-8/23/2013) 270B-101.1 to 270B-103 (Concord) -(6/17/2013-8/2/2013) Anomaly Remediation 256-3A to 257-3 (8/26/2013-8/30/2013)

  11. Div 10(300 Line) – August Outages Station 319 NEUP (8/15/2013-10/25/2013) Station 323A NEUP Station (8/5/2013-10/7/2013) Station 313 MPP Station (8/12/2013-8/30/2013) NEUP Tie-Ins 322-2 (8/20/2013-8/30/2013) 325-2 (8/15/2013-8/21/2013) Station MaintenanceSta 303 – MPP (8/5/2013-8/10/2013) 317-1 - Pig installation (8/19/2013-8/29/2013) Station 321 NEUP (7/15/2013-8/5/2013) Maintenance Pigs321-1 to 325-1 (8/30/2013)

  12. Div 5 & 6 –September Outages Maintenance Pig Carthage Line (9/17/2013) (M) Station 40 Maintenance(9/2/2013-9/20/2013) ILI Pigging MLV823-1 to 827-1 (9/10/2013)(M) ILI Pigging MLV507G-100 to 507G-109 (9/25/2013)(M) ILI Pigging 409A-1101 to 409A-1102 (9/24 /2013-9/26/2013)

  13. Div 8 & 9 – September Outages ILI Pig110-2 to 114-2S (9/1/2013-9/2/2013) (M) Rosehill Class Change 558 to 860 (Line 2 & 3) (7/15/2013-11/1/2013) Anomaly Remediation 69-2 to 78-2 (9/23/2013-10/17/2013) Pressure test 63-4 to 64-4 (9/1/2013-9/30/2013) (M)

  14. Div 10(200 Line) – September Outages Anomaly Remediation 219-2 to 307-1 (9/1/2013 - 12/1/2013) 219-3 to 307-2 (9/1/2013 - 12/1/2013) Anomaly Remediation 200-4 to 219-4 (11/16/2011-12/31/2013) 205-2 to 206-2 (8/15/2012-10/31/2013) 207-2 to 208-2(8/15/2013-10/31/2013) 211-1 to 212-1(9/1/2013-9/15/2013) 211-2 to 212-2(9/15/2013-9/30/2013) Station 219 Maintenance MPP (9/8/2013-9/27/2013) Pipe Replacement MLV 204-4 (8/5/2013-10/11/2013) MLV 212-4(8/5/2013-10/11/2013) Station 209 Maintenance MPP (9/4/2013-11/8/2013) Hydrotest MLV 200-1A to 201-1 (7/18/2013-9/4/2013) MLV 203-1 to 204-1 (8/5/2013-10/11/2013) MLV 208-3 to 212-3 (8/2/2013-12/19/2013) 213-3 to 214-3 (8/5/2013-10/11/2013)

  15. Div 10(200 Line) – September Outages Station Maintenance Sta. 264 (9/30- 10/4) Unit Maintenance Sta. 241 (9/9/2013-9/13/2013) Sta. 261 (9/5/2013 - 9/13/2013) Sta. 261 (9/16/2013 - 9/20/2013) Sta. 261 (9/3/2013 - 9/4/2013) Sta. 261 (9/30/2013- 10/4/2013) Sta. 264 (9/23/2013- 9/24/2013) Sta. 264 (9/25/2013- 9/26/2013) ESD Sta 230C (9/17/2013) Sta 237 (9/24/2013) Sta266A (9/17/2013 - 9/18/2013) ILI pigging 261B-101.1 to 261B-102 (Springfield) (9/24/2013-9/25/2013) Class Change 230B-200 Niagara Spur Loop Line (9/16/2013-10/7/2013) Line lowering 260A-100 (Northampton) (M) (9/3/2013-9/5/2013) Anomaly Remediation 248-2 to 249-2 (9/16/2013-10/5/2013) 258-1 to 259-1 (9/3/2013-9/13/2013)

  16. Div 10(300 Line) – September Outages Meter Station Upgrade Meter 020207 (Mahwah) (9/2/2013-9/5/2013) Station 319 NEUP (8/15/2013-10/25/2013) Station 323A NEUP Station (8/5/2013-10/7/2013) Maintenance Pigs319-1 to 321-1 (9/15/2013) 319-1 to 321-1 (9/20/2013) 321-1 to 325-1 (9/30/2013) NEUP Tie-Ins Sta. 321 (9/16/2013-9/30/2013) 327-2(9/15/2013-9/21/2013)

  17. We welcome your feedback/questions • Suggestions for improvements to this meeting • Are the meetings beneficial? • Is additional information needed? • Questions after the meeting? • Other? • Email to one of the following: • Your scheduler • PASSKEY Portal