Hybrid & Module Testing Status Week of 5/2-5/6
UCSB Hybrid Testing Status Failing Hybrids Over-counted
This Week 4 with shorts in PA Lithography errors-fixable Cumulative 7 with Shorts in PA Repairable 1 Major Scratch in PA 1 Smashed APV-PA Bonds Repairable 2 Failed Inspection Never should have sent 1 Broken Ceramic 1 Bad Bond Feet 1 Weak Wirebonds 1 Too Many Opens 2 with unknown failure UCSB Hybrid Testing Failures
UCSB Hybrid Testing Issues • Need to finish validation of new software • Bruno contacted about bugs/features • Need to add automatic upload of data to new software • Hybrids with shorts need repairing • Once repaired need to keep bookkeeping straight
This Week None Fixed 1 module Found the problem with another Fixable, need to ship to FNAL for solder repair Cumulative 1 with >2% Bad Channels Debris on sensor 1 Bad DCU Fixable, soldering problem 1 HV Shorted to CF Frame FIXED!! 2 with >20 mA Bias Current 1 leaky pinhole 1 scratched sensor UCSB ARCS Testing Failures
This Week (8105-8167) one unexpected pinhole - pulled (mod 8140 # 3) 8 PHL-: 8138 (#92), 8139(#430), 8144(#438), 8146 (#58), 8152(#78), 8153(#645), 8154(#650), 8167(#119) 1 SHT ARCS 8.0 has been installed and is being tested; looks ok so far Cumulative (7835-8167) 2 grade “B” (mishandling; missing bonds on p/a) 7970 - breakdown current behavior @430V Total of 11 pinholes Cumulative (7702-8167) 2 grade “B” (mishandling; missing bonds on p/a) 2 grade “F” mishandling 7970 - breakdown current behavior @430V FNAL ARCS Testing Failures
FNAL LT Testing Issues • Modules 30200020008064 – 8100 were tested during May 3-May 10 period. • Modules 30200020007961 - 7970 were retested. • All modules successfully passed LT with grade A. • All runs were performed with 2 CCU6’s. • Currently working on configuring 2 CCU25’s • (0x14 and 0x11).
Weekly Cumulative fFail Pass Fail Pass % Pass L12pu 0 0 0 0 0.00% L12pd 0 0 12 0 100.00% L12su 0 0 0 0 0.00% L12sd 0 0 0 0 0.00% 9150 L34p 37 0 1 99.33% L56p 10 0 104 0 100.00% R5N 0 0 0 0 0.00% 00 00 00 R5S 0 0.00% R6 0 0 0 0 0.00% R7 0 0 0 0 0.00% Total 47 0 266 1 99.62% FNAL LT Testing Status