An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EPMRCost and ScheduleNovember 17, 2009 Len McMaster AIM Program Deputy Hampton University len.mcmaster@hamptonu.edu 757-570-6902 304-856-1118

  2. Schedule History

  3. Schedule History (con’t.)

  4. Mission Costs through Phase C/D

  5. Phase E Costs Jun ‘07 – May ‘08

  6. Total Baseline Mission Costs – May 2009

  7. Lessons Learned • Place high importance on cost (as well as science), including timely decisions • Significant cost savings realized by early decision to … • Change Bus provider from new to 5th gen design • Eliminate IPA and HAPS • Descope SHIMMER instrument • Reduce CIPS cameras from six to four • Cost share delayed delivery of SOFIE • … • Don’t impose more stringent requirements than initially required/proposed, e.g., EEE parts upgrades, additional reviews, … • 20% Management Reserves was sufficient except for dealing with issues relating to launch loads increase

  8. Back-Up Use of Management Reserves, FY09 costs, Extended Mission Cost Plan

  9. 30 Reserve (% CTG) 20 10 Funding Reserve (without costs due to revised launch loads or schedule reserves) Reserve Encumbrances and Liens Reserve ($K) 37% 2004 2005 2006 Phase C/D

  10. Monthly Cost Plan-Actuals-Variance FY09 Estimate to Complete Plan Extended Mission Plan Actuals 275K $K -24K Variance FY 2009

  11. Cumulative Cost Plan-Actuals-Variance FY09 Extended Mission Plan Estimate to Complete Plan 3.58M Revised Plan Actuals -98K Variance FY 2009 Cumulative Variance: - reset to beginning of extended mission period (June 1, 2009)

  12. Extended Mission Monthly Cost Plan OOMPS mod (re-planned) Actuals $K Extended Mission Plan Variance FY2009 FY2010 FY2011 FY2012