An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PMG AgendaFeb 3, 2000 • Overview • Project Manager’s Report – Tuts • Fallback options – Weerts • Silicon Support Cylinder Modifications - Cooper • Fallback Options & Installation - Kotcher

  2. Completed Reportable Milestones • 3 early • 3 on schedule (|.2w|) • 7 late

  3. Near Term Reportable Milestones

  4. Status Overview since last PMG • Silicon sensors • Axial (3 chip) • No problems • 90deg (6 chip) • Micron delivery an issue (sputterer problem at Micron, being fixed) • Micron delivery paces • Fallback – accept lower grade detectors • 2deg (9chip) • Production going well (last batch 19/25 passed) • Full delivery in April • F wedges • Proceeding well at 50-60% yield at Micron (last batch 5/6 passed) • Received 5/75 sensors from Eurisys • H wedges • 60 more on order

  5. Silicon • HDI • Getting sufficient HDI’s to keep pace with production is a problem • Expediting additional HDI orders • 2nd vendor for bonding, Silitronics, looking good • H wedge • 2 HDI left, as expected • Production stops for 4 wks • 2deg (9chip) • Out of HDI’s, rounding up what is available 5-9 • F wedge • Almost out of HDI’s

  6. Silicon • Ladder & Wedge production • Axial (3 chip) • Picking up next week • 2deg (9chip) • Production lagging, out of HDI’s • 90deg (6chip) • Paced by Micron delivery • F wedges • Limited by HDI availability • H wedges • Limited by HDI availability

  7. Production Status

  8. Fiber Status • Fibers • Waveguide production going well • 175 bundles pulled & cut • Cylinders 8, 7 complete • Nesting cart is being measured; delays by about 4 weeks • 8a and 7a installed and glued • Final stiffness tests in progress • Start assembly next week, 2/7 • Flex circuits still a concern, delaying complete start of VLPC cassette production • Compunetics 100pc order nearly complete – 34 good, 31 to go • 1st production cassette under test • Many components done while awaiting flex circuits (~20%)

  9. Fiber Tracker Status • Ribbon Production • Continues

  10. Fiber Tracker Status • Ribbon Mounting • Continues • C8 and C7 Done • C6 axial started

  11. Status Overview • Preshowers • Some schedule re-arrangement, net speedup • Tracking Electronics • Some (2-4wks) slippage in layout and vendor production, worry here……. • Calorimeter Electronics • 98% of preamps (59kch) in hand • Power supplies complete • 80% of packaged SCA’s in hand, will need to order 5k more • Small layout problems cause 6 week delay to BLS schedule • Installed 2 power supplies & 16 card of preamps in detector with online controls for p.s.

  12. Status Overview • ICD • Module testing underway • Preamps in hand, motherboard ordered • Central Muons • Commissioning continues • First ½ truss in D0 Hall • Forward Muons • Trig Pixels: Proceeding well on schedule. • See no problems meeting April completion date • MDTs: @Dubna completed. Being shipped in heated container. • Production on A MDTs layer has started • C MDT parts presently most critical items (panels, etc)

  13. EMC north truss, being taken apart for transport to D0. January 31, 2000

  14. Trigger pixels The forward muon trigger planes: 3 planes: A, B, C with 16 octants ( north & south) each All pixel counters are at FNAL Layers A & C are completed Layer B started

  15. MDT chambers & octant assembly The tracking planes: MDT production at Dubna complete ( shipping) A layer assembly done

  16. Status Overview • Trigger & DAQ • Proceeding well • Delays in some in 12MCM boards ( stereo CFT, CPS, FPS), because of engineering • Online • Manpower in good shape • No schedule concerns, not on critical path • Being tapped for manpower in other systems

  17. Summary • Concerns • HDI deliveries • Silicon testing • Fiber flex circuits for VLPCs • Forward muon installation • M&S cost contingency continues to dwindle • On the horizon • Lehman review…….