An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2014 Fire ProcurementDispatch update

  2. R6 Mob guide Reminder Chapter 20 Ordering Considerations In the event VIPR DPLs are exhausted and/or the closest available VIPR DPL resource is estimated to travel 10 or more hours to the incident, orders for the following resources should be returned to the local unit and attempt to be hired locally via incident-only EERA: • Potable Water Truck • Gray Water Truck • Refrigerated Trailers • Heavy Equipment (Dozer w/transport & Excavator w/transport) • Misc. Heavy Equipment (Feller Bunchers, Masticators, Skidders, Road Graders) • Fuel Tenders • Chippers All other VIPR resource orders should be placed with NWCC when the DPLs are exhausted.

  3. Aviation - Helicopters • R6 CWN Type III Helicopters • Year 4 of 4 • Status Quo • R6 Exclusive Use Type III Helicopters • New Awards Pending • 4 Bases: John Day, Prineville, Wenatchee (2) • Short Haul Capability for Wenatchee (1) and John Day in 2015

  4. Aviation – Light Fixed Wing • CWN Light Fixed Wing • Year 2 of 4 • Air Attack • LaGrande & Wenatchee – Year 3 of 3 • Redmond & Klamath Falls – Year 2 of 3 • MAPs extended from 70/75 days to 120

  5. VIPR Update • New Regional IBPAs: • Fuel Tenders • Heavy Equipment • Mechanic w/Service Trucks • Fallers • New National IBPAs: • Commo Trailer • GIS Trailer • Office Clerical Trailer • Helicopter Trailer • Rollovers Ongoing

  6. Enterprise bpa New BPA in place, no significant changes. Dispatch: • Please monitor AD & Employee orders to ensure documentation is submitted to FACT • Package needs to be started & returned by Host Center • Host Center sends payment package to FACT Tracking Sheet – see handout.

  7. Laptops • Smartsource BPA renewed • Ipads added • No other changes

  8. Training Schedule • ICPI Refresher – April 16-17 (8 hours) • Dispatch Road Show and Fire Purchasing: May 6 – La Grande OR May 7 – Wenatchee WA May 13 – Portland OR May 14 – Roseburg OR May 15 – Prineville OR Dispatch Updates 0900 to 1130 Fire Purchasing Training 1230 to 1630

  9. ITEAM History • Created in 2009 for the Forest Service Region 6 • Replaced decommissioned EERA Database • Primary Purpose – “source list” for non-VIPR resources Target Audience: • Dispatch • Procurement • Fire & Aviation Mgt. (FAM)

  10. ITEAM Current Scope: • Master List • EERAs • Dispatch • Contractor Employee Quals Changes for 2013: • None!!!

  11. ITEAM Getting Access: • Handout • Available at: http://www.fs.usda.gov/goto/r6/workingtogether/contracting/fact - Access Guide in both CO & Dispatch Resources links Roles: • Dispatch – Read Only • CO

  12. Master Lists Optionalsource for locating resources: • Primary source for drivers, toilets, handwash stations, & tents. • Should consider these before open market • Alternative to mob’ing IBPA resource that cannot meet date/time, but – • Cannot be used in lieu of IBPAs!

  13. Master lists Master Lists are: • Generated by FACT • Already negotiated • SAM validated Master Lists are not: • Signed preseason • Binding • Numbered New vendors/sources should be sent to FACT

  14. Dispatch tab Primary Function = locate Master List resources • Review Search Options Selecting a Resource: • No DPL or formal selection process • Consider: • Price • Proximity • Date/Time Needed

  15. EERA • Remember these are incident-only! • Requires new EERA for each incident • Master List is not signed • Note: When the EERA is issued it includes all resources on Master list • EERA will require both Gov & Kr signature each order/incident • Cannot reassign EERA • New incident = new EERA

  16. EERA Procurement & Dispatch need to coordinate local process Options: • Dispatch can generate unsigned EERA in Dispatch Tab • Still needs signature to be valid • Work with local unit to develop process • Procurement or Buying Team manages EERA process

  17. EERA Email Option: • Can email unsigned EERA directly to vendor from ITEAM • Help facilitate signature process • Keeps record of orders • Will not save changes/edits in ITEAM! • Maintain hard copies as needed

  18. EERA Attachments Attach the following: • General Clauses to EERA • Wage Determination • R6 Supplemental Terms & Conditions • Vendor Code Information Sheet (if not in SAM) Attachments available at: 1. R6 Website: http://www.fs.usda.gov/goto/r6/workingtogether/contracting/fact 2. Documents Tab in ITEAM