1 / 32

SW Project Management Project Schedule and Budget

SW Project Management Project Schedule and Budget. INFO 420 Glenn Booker. Grand finale. Developing the project schedule and budget is the grand finale of the project planning process – our ultimate goal We just defined the tasks and estimated their duration (effort)

betty_james
Download Presentation

SW Project Management Project Schedule and Budget

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SW Project ManagementProject Schedule and Budget INFO 420 Glenn Booker Chapter 7

  2. Grand finale • Developing the project schedule and budget is the grand finale of the project planning process – our ultimate goal • We just defined the tasks and estimated their duration (effort) • Now identify the sequence of tasks, interdependencies, and staffing needs Chapter 7

  3. Project cost management • The budget is determined from the project schedule, the cost assigned to tasks, and other indirect costs or resources • Project cost management includes • Cost estimating for tasks and their resources • Cost budgeting for the whole project • Cost control – define processes Chapter 7

  4. Rolling up costs • Since our tasks were organized into phases and deliverables, we can roll up (summarize) costs to any level desired • Cost per deliverable • Cost per phase • Cost of the whole project • The sponsor needs to approve these costs Chapter 7

  5. Developing project schedule • A key sanity check is that each of the estimates for each task is really reasonable according to the experts in that activity • GIGO applies here, not just to programming! Chapter 7

  6. Project schedule tools • Tools to show a project schedule include • Gantt chart • Project network diagram • Activity On the Node (AON) diagram • Critical path analysis • PERT charts • Precedence diagramming method (PDM) • Critical chain project management (CCPM) Chapter 7

  7. Gantt chart • The Gantt chart is probably the most widely used project management tool • Time is the X axis, from days to years • The current date is readily visible • Tasks are on the Y axis • Bars represent WBS tasks • Milestones are diamond shapes • An inset bar can show actual work progress Chapter 7

  8. Basic Gantt chart Chapter 7

  9. Project network diagram • Project network diagrams are also based on the WBS, but also show more info on task sequence or dependencies • Many also show when tasks must start or stop in order not to affect project completion date • This can help decide resource assignments needed for critical tasks Chapter 7

  10. Activity On the Node • Activity On the Node (AON) diagrams represent the flow of tasks needed to complete the project • Tasks are nodes (boxes) • Arrows show the order in which they occur • The duration of tasks isn’t directly visible under AON, only time order Chapter 7

  11. Activity On the Node • Tasks can be predecessors, successors, or in parallel • Predecessor tasks must occur before another task • Successor tasks must occur after another task • Parallel tasks may occur at the same time as another task Chapter 7

  12. Critical path analysis • Given an AON, critical path analysis determines which activities are directly connected to achieving the project schedule • They are the critical path, which can change • Analytically, find the duration of each path through the AON diagram Chapter 7

  13. Critical path analysis • The path with the longest duration is the critical path (and the project duration) • If any tasks on the critical path are delayed, the overall project completion will be delayed • Tasks not on the critical path may have a non-zero amount of slack or float, which is the amount of duration they can slip without affecting the project Chapter 7

  14. Critical path analysis • A manager might add resources to tasks on the critical path, if that will actually help finish them sooner • This technique can be called expediting or crashing the project • Fast tracking the project is done by making tasks parallel that weren’t Chapter 7

  15. PERT charts • PERT is the program evaluation and review technique, developed in the 50’s • Often seen with CPM, or critical path method • A PERT chart also uses the AON graphic notation, but uses a different approach for estimation Chapter 7

  16. Styles of PERT nodes Chapter 7

  17. PERT charts • For each task, estimate the lowest (optimistic), most likely, and highest (pessimistic) durations, then use • estimate = (low + high + 4*likely)/6 • The critical path analysis can be done based on these estimates Chapter 7

  18. Precedence diagramming method • The precedence diagramming method (PDM) adds to AON by showing the key sequence relationships • Finish to start (most common, sequential) • Start to start • Finish to finish • Start to finish Chapter 7

  19. PDM node relationships From Fig. 7.5 Chapter 7

  20. PDM • PDM can also show lead and lag times for activities • Lead time is an amount of time a task can start before the end of its predecessor • Lag time is the amount of time a task must start after the end of its predecessor • Hence lag time = negative lead time Chapter 7

  21. Critical chain project management • Critical chain project management (CCPM) is a newcomer (Goldratt, 1997) • It assumes that all estimates are inflated • We still finish projects late because • We wait until the last minute (student syndrome) • Projects fill the time available (Parkinson’s law) • Resource contention Chapter 7

  22. CCPM • CCPM takes that buffer from each task, and puts in in larger blocks where needed • How? Estimate tasks so that you only have a 50% chance of completing them on time • Then take half of the difference in task time, and put that into a buffer at the end of the project Chapter 7

  23. CCPM • Yes, you have to estimate each task twice • Once normally, and once for 50% chance completion • CCPM also accounts for resource limits, by identifying the resources for each task and buffers for each type of resource Chapter 7

  24. PM software tools • There are several project management software tools for developing and managing schedules • Microsoft Project is the de facto standard • Planner and OpenWorkBench are open source tools • Ok, so Project doesn’t have much competition… Chapter 7

  25. PM software tools • Often projects are planned in detail only a few months in the future, a rolling wave approach • There’s an outline of the rest of the project, particularly for planning long lead time items Chapter 7

  26. Project budget • The budget is straightforward to develop, once the schedule has been determined • Determine the type of resource(s) needed for each task, and how many of them are needed for its duration (0.1, 2.5, whatever) • Find the cost of each resource type ($/hr), and multiply that by how many and the duration = cost per task Chapter 7

  27. Project budget • Check for overuse of resources – often not recommended to use 155% of a person’s time • To find the cost of each resource*, assess their typical annual salary**, divide by 2000 (hours per work year), and multiply by 2.5 (to account for overhead expenses) * This is a heuristic. ** You could look for salary surveys. Chapter 7

  28. Project budget • So if a software engineer averages $60k/year, their hourly rate is about $30/hr • Actually, a normal work year is 40*52 = 2080 hours, but we’re just getting a rough estimate • Multiply by 2.5 to get a labor rate of $75/hr • This is the ‘true cost’ in the text Chapter 7

  29. Other costs • Labor is the biggest cost on most projects, but other costs should be considered • Indirect costs – are admin assistants, facilities, insurance, etc. paid by the project, or from overhead? • Sunk costs – from previous bad projects • Learning curve – might be covered by prototypes Chapter 7

  30. Other costs • Reserves – most projects keep back a 10-15% reserve from the total actual budget, in anticipation of some cost overruns • Project-specific hardware and software – plan for infrastructure costs (servers, network equipment, software) which aren’t part of normal office & facility environment • Travel, e.g. to the customer? Chapter 7

  31. Resource allocation • Again, make sure that individuals aren’t scheduled for over 100% of their time • Also consider resource leveling • Are there times when people are needed, then not, then needed again? • What will those people do in the middle? Chapter 7

  32. Baseline plan • Once all these issues have been identified and agreed upon, you have the baseline project schedule, which feeds the project plan • All measurements of ‘planned versus actuals’ hinge upon this plan! Chapter 7