Activities of TOF @CERN(Mars-May 2008). Jinsook Kim, Yongwook Baek. Activities of TOF assembly@CERN(Mars-April 2008). SM16: Completed LV cables installation HV cables tested VME 4 crates test & mounted FEA cards & record ID Amphenol cables done (both) FEAC cards & cables installation
E N D
Activities of TOF @CERN(Mars-May 2008) Jinsook Kim, YongwookBaek
Activities of TOFassembly@CERN(Mars-April 2008) • SM16: Completed • LV cables installation • HV cables tested • VME 4 crates test & mounted • FEA cards & record ID • Amphenol cables done (both) • FEAC cards & cables installation • Gluing done for both sides • Pulser test : done
Activities of TOFassembly@CERN(Mars-April 2008) • SM17& SM18 : 100 % done • Cooling pipe • Aluminum frame done • gas leak test • Put mylar to protect interface cards • FEA cards & recode ID • LV cables installation • HV cables tested • VME 4 crates test & mounted • FEA cards & record ID • Amphenol cables done • FEAC cards & cables installation • Gluing done for both sides • Pulser test : done • Move to P2
Activities of TOF@CERN(May 2008) • Check using test program : • Control cable connections • DRM connection • Fix & test : • Slow control cables • TTC signal cables • Installation : • Grounding cables • LV power cables • Optic fiber links
Summary & Milestone • Summary (1 post doc. & 1 students) • The assembly of TOFs has been completed in time. • All SMs have been installed @P2 • Milestone • Commissioning • Cosmic run (magnet on) Period: 2nd & 3rd week of June