Activities of TOF assembly@CERN(Feb. 2008). SM15: Completed LV cables installation HV cables tested VME 4 crates test & mounted FEA cards & record ID Amphenol cables done (both) FEAC cards & cables installation Gluing done for both sides Pulser test : done.
E N D
Activities of TOFassembly@CERN(Feb. 2008) • SM15: Completed • LV cables installation • HV cables tested • VME 4 crates test & mounted • FEA cards & record ID • Amphenol cables done (both) • FEAC cards & cables installation • Gluing done for both sides • Pulser test : done
Activities of TOFassembly@CERN(Feb. 2008) • SM16 : 20 % done • Cooling pipe • Aluminum frame done • gas leak test • Put mylar to protect interface cards • FEA cards & recode ID SM15 SM16
Summary & Milestone • Summary (1 post doc. & 2 students) • Cabling : FEA, FEAC cards & Amphenol cables for SM15 • Test & cabling : LV cables, HV cables, control cables SM15 & SM16 • SM15 : 100 % Completed • SM16 : 20 % Completed • Total : 10 SMs installed@pit + 5 SMs waiting for next installation • 86% of milestons have been achieved. • Milestone • Assembly@CERN : 3 SMs to be done • Next installation period : • 5 SMs (Mars 10th ~ 14th) • 3 SMs (April 7th ~ 11th)