STRATEGIC PETROLEUM RESERVE BAYOU CHOCTAW CAVERN 20 REPLACEMENT

STRATEGIC PETROLEUM RESERVE BAYOU CHOCTAW CAVERN 20 REPLACEMENT. BC-102. BC-20. 2. BAYOU CHOCTAW CAVERN 20 REPLACEMENT CRITICAL DECISIONS. CD-0 07/21/09 (A) Approves Mission Need CD-1 03/09/10 (A) Approves “Alternate Selection and Cost Range” Prerequisites

blaze
Download Presentation

STRATEGIC PETROLEUM RESERVE BAYOU CHOCTAW CAVERN 20 REPLACEMENT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. STRATEGIC PETROLEUM RESERVE BAYOU CHOCTAW CAVERN 20REPLACEMENT 1

  2. BC-102 BC-20 2

  3. BAYOU CHOCTAW CAVERN 20 REPLACEMENTCRITICAL DECISIONS CD-0 07/21/09 (A) • Approves Mission Need CD-1 03/09/10 (A) • Approves “Alternate Selection and Cost Range” • Prerequisites • Completion of Conceptual Design Report(s) • Development of Acquisition Strategy • Evaluation of Project Risks and Hazards Analysis • Value assessment (e.g., need to perform Value Engineering Study) • Approves initiation of engineering design and land acquisition • Approves acquisition of LLE 3

  4. BAYOU CHOCTAW CAVERN 20 REPLACEMENT EXECUTIVE SUMMARY CD-2 05/27/11 (A) • Approves “Performance Baseline” • Prerequisites • Completion of Project Execution Plan • Establishment of Performance Baselines • An External Independent Review • Approves acquisition of construction in FY 2011 CD-3 05/27/11 (A) • Approves start of construction CD-4 09/07/12 (Submission) 01/15/13 (Approval) • Approves start of operation, turnover to Operations and Maintenance 4

  5. STRATEGIC PETROLEUM RESERVE CAVERN REPLACEMENT ATBAYOU CHOCTAW • ACTIONS & ACTIVITIES: • Land Acquisition – Corps of Engineers • Just Compensation Letter was sent to P/L Olefins and the Wilbert’s • 90 Day Notice to Vacate Sent to P/L on 3/24/11 to vacate by 6/27/11 • Condemnation Letter Sent to the Wilbert’s on 4/13/11 • Negotiations completed on 4/25/11. File sent to Legal on 4/26/11 • D-T package to Corps’ Division Office 7/9/11 • Right-of-Way available on 10/31/11 • PL Olefins working on the removal of its ethane (personal property) 5

  6. STRATEGIC PETROLEUM RESERVE CAVERN REPLACEMENT ATBAYOU CHOCTAW • ACTIONS & ACTIVITIES: (cont) • AFC Facilities Phase I Design is Complete • 100% Phase II Design is Complete • Well LLE has been Awarded and is Being Manufactured. • Bids Received for Phase I Construction Package 6

  7. STRATEGIC PETROLEUM RESERVE CAVERN REPLACEMENT ATBAYOU CHOCTAW • LOOK AHEAD • AFC Facilities Phase II Design • Pre-Qualify Drilling Mgmt Services Contractor • Complete Manufacture of Drilling LLE • Award Phase I Facilities Construction • Complete Condemnation Process for Land Acquisition 7

  8. STRATEGIC PETROLEUM RESERVE CAVERN REPLACEMENT ATBAYOU CHOCTAW • CONCERN • P/L has notified USACE / DOE that Relocation Efforts may take up to 6 Months • Negotiations are Ongoing on this • Mitigative Measures are Being Identified and Implemented to Maintain Overall Project Schedule 8