Market Systems Release Update Modifications Committee Meeting 53 February 6 th 2014. SEM R2.4.0 – May 2014. Regulatory approval for the release scope was received on November 18 th and the approved scope was published to the industry on November 20 th. SEM R2.4.0 – May 2014 - Milestones.
E N D
Market Systems Release Update Modifications Committee Meeting 53 February 6th 2014
SEM R2.4.0 – May 2014 Regulatory approval for the release scope was received on November 18th and the approved scope was published to the industry on November 20th.
SEM R2.4.0 – May 2014 - Milestones Final design comments closed Feb 4th Publication of MPUD Feb 12th Software delivery Feb 28th System Integration Test Execution Mar 3rd to Apr 25th Market Test Execution Apr 9th to Apr 25th Deployment * May 16th * subject to successful completion of all testing.
SEM R2.5.0 – October 2014 The release cut-off date for the SEM R2.5.0 release is: Friday February 21st, 2014