An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HFTBeam PipeandSafety D. Beavis (BNL) HFT Workshop March 10-11, 2009 BNL

  2. Schedule

  3. Cost • Estimate $292,000 with 20% cont. for a total of $350,000 • Actual $327,116

  4. Comments • PHENIX pipe came in one week ago • They are confident it will be installed • There was trouble with fabrication of PHENIX pipe and this is causing a few weeks delay in our customer prints to address issues • PHENIX pipe length out of tolerance and roundness was just acceptable. • The pipe was “dirty” inside • Although nearly on schedule there is still lots of opportunities to be late for our pipe

  5. Remaining items • Outside sections--design and order • Bellows and mounts • Heating blankets • Blanket insertion device

  6. HFT Safety • Have a pHAD (preliminary Hazard Analysis Document) • pHAD and Design Questionnaire sent to safety in C-AD on Sept. 30, 2009 • Update to a HAD for CD-2 • Send an updated version of pHAD (HAD) to safety people in about 2 months

  7. Safety • Individual items can be addressed as needed • Fire test of carbon fiber is pending (FGT) • Paperwork found for lifting fixture (550 #) • Others as they come up