1 / 0

Town of Lunenburg

Town of Lunenburg. Renovated DPW Facility. Building Committee. Chair: Vice Chair: Clerk: Members: Town Representatives:. David MacDonald Joanna Bilotta-Simeone Jay Simeone Jimmy Breault Jan Carrier Steve deBettencourt Leigh Mezetti Kerry Speidel Jack Rodriquenz Amanda Moore.

brina
Download Presentation

Town of Lunenburg

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Town of Lunenburg

    Renovated DPW Facility
  2. Building Committee Chair: Vice Chair: Clerk: Members: Town Representatives: David MacDonald Joanna Bilotta-Simeone Jay Simeone Jimmy Breault Jan Carrier Steve deBettencourt Leigh Mezetti Kerry Speidel Jack Rodriquenz Amanda Moore
  3. 2010 Feasibility Committee Objectives To evaluate the current site and determine if it is adequate in terms of size and location for current level of operation. If the current site is determined to be inadequate, the Committee should detail site deficiencies and identify remedies to the best of its ability. Evaluate the current facility to determine suitability for current level of operation. If the current facility is determined to be unsuitable, the Committee should detail deficiencies and identify remedies to the best of its ability. If the Committee determines that the current facility is inadequate, it should identify possible sources of revenue to make needed improvements. Specific attention should be paid to Green alternatives
  4. Old Facility
  5. Feasibility Committee Members: Town Representatives: David MacDonald Pat Slattery Steve Powell Dan Proctor Jay Simeone Leigh Mezzetti Kerry Speidel Jack Rodriquenz
  6. Public Works Under One Roof Sewer & Technical Support Vehicle Maintenance Parks& Recreation Highway Facilities Cemetery
  7. Updates to Existing Garage Compliant with building codes Updated electrical service Dedicated vehicle maintenance area Insulated electric overhead garage doors Lighting fixtures Energy efficient heating system Ventilation system Carbon monoxide detectors Updated security system Metal stairs to access mezzanine area ADA bathroom
  8. New Garage Doors Insulated Electric Energy cost savings
  9. Lighting Less fixtures More illumination Cost efficient
  10. Heating System Compact High efficiency
  11. Ventilation System Clean-air
  12. Carbon Monoxide System Detects toxins Alarm system
  13. Security System Tied into public safety dispatch
  14. Stairs/ Mezzanine Updated Clean Additional storage
  15. Bathrooms ADA compliant Shower
  16. Office Area Old Office New Office Insufficient office space for all staff members Poor HVAC system Not handicap accessible No meeting/conference room Insufficient/unreliable communication systems Break room located in improperly ventilated mezzanine area Insufficient storage for files and supplies Out dated furnishings Removed center wall to expand office New HVAC system Handicap accessible restrooms Conference/ training room New communication systems and wiring Break room on ground floor New filing cabinets and closets. New carpet and office furniture Updated all code issues
  17. Reception Area Waiting space for guests
  18. Administrative Area Additional filing Separate from reception area
  19. Director’s Office Privacy Space for conferences
  20. Department Offices Facilities Manager Highway Supervisor Sewer Park Department Cemetery
  21. Conference Room Safety training Division meetings Cemetery Park Sewer DPW Staff
  22. Employee Break Room Up to code Space for all employees
  23. New Addition 4800 sq. ft. steel pre fabricated building Heating and ventilation system Electrical service and lighting fixtures Floor drainage system with holding tank Vehicle washing station Sufficient room for the large trucks with plows, loaders, and seasonal equipment
  24. Exterior Space for all vehicles
  25. Garage Doors Insulated Electric
  26. Lighting Cost efficient
  27. Wash Station/ Drainage Vehicle maintenance
  28. Containment Tank Reduce contaminants to environment
  29. Electrical System Up-to-date
  30. Carbon Monoxide System Detects toxins Alarm system
  31. Ventilation System Clean-air
  32. Heating System Compact High efficiency
  33. Fire Alarm Dedicated phone line Tied into public safety dispatch
  34. Cost Savings Revised the language in the RFP to reduce the fees and expenses in the bidding process Three part bid process Negotiated a one time design fee for Architectural services Used State Bid approved vendors Worked with Unitil Electric to qualify for rebates Committee members, the DPW Director, and the Facilities Manager acted as Clerk of Works on the construction site
  35. Budget
  36. Finishing Touches Garage exterior will be painted in Spring. Special thanks to the DPW employees for painting the interior of garage. Re-grading parking area New Awning over office entrance Volunteer services to create a rain garden consistent with Storm water process Town has the ability to sell both the West St. (Park) and Holman St. (Cemetery) properties
  37. Board of Selectmen Finance Committee Public Safety Officials Public Works Personnel Park Commission Cemetery Commission All other Departments involved in the approval process Thanks to…
  38. Special Thanks To… , the residents of Lunenburg who supported this project from the beginning You
More Related