PACS Management, Funding and Schedule. Otto H. Bauer MPE Garching. Important Events. CAPTEC audit of on-board S/W completed (IFSI, UVIE, CSL) Reports are available Debriefing meeting with Project still missing !? DRB´s for AVM/CQM completed
E N D
PACS Management, Fundingand Schedule Otto H. Bauer MPE Garching PACS Management, …
Important Events • CAPTEC audit of on-board S/W completed (IFSI, UVIE, CSL) • Reports are available • Debriefing meeting with Project still missing !? • DRB´s for AVM/CQM completed • DRB on 22/23 Nov: FPU delivered to Astrium on 26 Nov 04 • Delta-DRB for WE on 8 Dec 04: WE delivered on 10 Dec 04 • Latest developments • CQM FPU mounted on OB: NCRs against all L0 straps • WE: ILT EGSE test succesfully completed • WE: CCS: many problems with missing cables, bridge files • WE: mounted on SVM panel, WIH integrated, bonding ok PACS Management, …
Funding/Contracts • MPE • Funding proposal (PACS Instrument) for 2005/2007 approved by DLR • CSL/OIP • PRODEX helped to solve severe Belgian funding problem (Dec 04) • IFSI • Italian ICC funding until end of 2005 approved by ASI • New contract for QM and FM manufacture approved, but not yet signed • IAC • Funding for QM and FM manufacture approved • UVIE • Funding secured until end 2005, but reduced travel money Impact on S/W testing PACS Management, …
FM Schedule I • WE has severe schedule problems: • Herschel DPU/ICU Meetings: Project, ASI, CGS, IFSI, 3 PI/PM´s: • 2 April 04, ASI / 27 May 04, IFSI / 29 July 04, CGS / 2+3 Sep 04, IFSI • Herschel/Planck CRISA Meetings: Project, CRISA, PM´s: • 8 July 04, CRISA / 26 Aug 04, CRISA • PACS DECMEC Meetings: Project, Prodex, CSL, OIP, MPE: • 16 June 04, ESTEC / 14 July 04, OIP AVM2 QM FM DPU Dec 04 end March 05 end Sep 05 SPU (EM) - end June 05 DECMEC mid Feb 05 ? end Sep 05 ? BOLC end June 05 mid Nov 05 PACS Management, …
FM Schedule II • Delivery dates to KT • FPU structural items cw 37/40, 2004 • Filters cw 5, 2005 • Chopper cw 7 + • Grating cw 9 + • PhFPU cw 30 • Ge:Ga detector array assembly cw 35 (CRE/module integration and test, detector array integration and test are on critical path) • FPU delivery to MPE cw 38 (mid Sep) • FM ILT 6 months • FM delivery to Project earliest midMarch 06 ! PACS Management, …