September 2011 Generation Resource Energy and Regulation Deployment Performance

September 2011 Generation Resource Energy and Regulation Deployment Performance. QMWG 10/11/2011. Month-to-Month NON-IRR GREDP – Energy Deployments. Resources below 85% threshold - No conventional resources scored below 85% for September. Month-to-Month NON-IRR GREDP – Regulation Deployments.

brooklyn
Download Presentation

September 2011 Generation Resource Energy and Regulation Deployment Performance

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. September 2011 Generation Resource Energy and Regulation Deployment Performance QMWG 10/11/2011

  2. Month-to-Month NON-IRR GREDP – Energy Deployments Resources below 85% threshold - No conventional resources scored below 85% for September.

  3. Month-to-Month NON-IRR GREDP – Regulation Deployments • Resource below 85% threshold • Resource 1 and 2 scored less than 85% for the first time.

  4. Month-to-Month IRR GREDP • Resources below 95% threshold • 27 failures • < 10 intervals – 8 IRRs • > 10 <= 100 intervals – 9 IRRs • > 100 intervals – 10 IRRs • Weighted Average GREDP – 87.17% • Average Deviation – 9.83 MWs

  5. IRR Total Intervals Scored – Month-to-Month

  6. GREDP Scenario Analysis

  7. Manual HDL/LDL Override Summary QMWG 10/11/2011

  8. Daily Summary Graph • For this analysis, we captured unique HDL/LDL overrides • An override is considered unique if that same Resource did not have an override within the last 10 minutes

  9. Daily Summary Table • There were 13 total unique overrides in August • As compared to 20 in July and 3 in August • All 13 were outage related • There were 3 separate outages requiring HDL overrides, 1 on each of the 3 days during which there were overrides • Number of overrides decreases if JOUs portions considered as a single Resource