An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CDF→ORKA: Preliminary Cost and Schedule Estimates Jonathan Lewis ORKA Meeting 2 March 2012 date corrected by PHG 11am Backup Slides 11 ff contain more on CDF Decommissioning and Display - PHG Jonathan Lewis ORKA Task Force 2 March 2012 2 pm

  2. Status J. Lewis--CDF Decomminssioning Status

  3. Scope • Remove CDF • Demolish all external muon walls • Dismantle central calorimeter • Refit plugs • Remove trackers • Excludes dismantling • Dismantle cable bridge • Refurbish Solenoid • Minor fixes to collision hall • Ignores filling 706’ area of assembly hall • Return to collision hall J. Lewis--CDF Decomminssioning Status

  4. Should I stay or should I go? J. Lewis--CDF Decomminssioning Status

  5. Assumptions and Caveats • This is a very raw first pass • Attempt to include all labor • Not fully scheduled • Many hanging tasks • Mostly my estimates • Input from Dave Erikson on time per foot to cut welds • Input from Dervin Allen on some demolition tasks from earlier scheduling work • Included labor for 1.5 year assumed duration • Full time building manager • Full time supervisor • 50% physicist J. Lewis--CDF Decomminssioning Status

  6. More caveats • Some short cuts • Iron workers treated as straight labor • Probably want fixed-price contracts • Minimal M&S • WAGs for crane rentals, etc. • Lots of things neglected • No ES&H • Assumes truck drivers, etc. covered by overhead • All costs are unburdened! • Given this level of understanding: 100% Contingency J. Lewis--CDF Decomminssioning Status

  7. Costs J. Lewis--CDF Decomminssioning Status

  8. Labor J. Lewis--CDF Decomminssioning Status

  9. Conclu$ion • $3M bottom-up cost matches top-down guess • More to do • Need to work out schedule J. Lewis--CDF Decomminssioning Status

  10. From: Jonathan Lewis Sent: Monday, March 05, 2012 11:49 PMTo: Peter H GarbinciusSubject: Re: Jonathan - please send me your slides from Friday's discussion of CDF Decommissioning & ORKA Here it is. While dismantling the central detector and the plugs is a big job, I know this is low. Another difference from previous estimates is that I have neglected disposal costs. My current understanding is that wire is not covered by the metals moratorium, so the cable is pretty much free to dispose of. Most of the steel would go to the railhead. The rest can go to a regular landfill, so that cost is pretty low. I'll work on revising the labor estimates in the next couple of weeks and get back to you. Regards, Jonathan (added by PHG) J. Lewis--CDF Decomminssioning Status

  11. Backup:CDF Decommissioning and DisplayJonathan Lewis2 March 2012

  12. Equipment Recovery • Done or in progress • Pisa: Crates, HV, Pulsars for Atlas, Magic, etc. • CMU: BSU PMTs for Tauwer (cosmic taus) • JLab: PES, CPR PMTs for Super Big Bite • Iowa: Bad CLC PMTs for novel calorimeter test • SNU: L3 Computers for LQCD • CD: Newest L3 computers for CDF Grid • Michigan: Crates, racks, etc. for KOTO • PREP: 10 pallets of NIM, Camac, HV • Yet to come • ASDQs for mu2e • PMTs for test beam • CSP counters for LBNE test • TSU counters for LAPD • Misc. counters and PMTs to Dubna for detector development • Plug HV for Prep J. Lewis--CDF Decomminssioning Status

  13. Mezzanine ready for demolition Gas racks gone Status 11/8 Scrap MGs and test magnet ready for removal 1st floor CR being cleared J. Lewis--CDF Decomminssioning Status

  14. Issues • Proposed experiments create significant uncertainty for D&D • Protoplasma • ORKA • Cable bridge plan assumed 20-year display phase • Removing bridge before detector makes detector removal trickier • Will wait until decision whether CDF will be rolled out • Scaling back display plan • Not putting plug on rails • Lab-wide task force • Evaluating interference between ORKA and IARC • Considering early roll-out to prepare for ORKA J. Lewis--CDF Decomminssioning Status

  15. Coordination with IARC • Electrical • Freeing up experimental power substation • Moving conduit for doorway • Mechanical • Coordinating moves of sprinkler and chilled water pipes for interferences with interconnects, etc. • Mezzanine removal • Planning (Dervin Allen) • Tours for A&E, contractors, etc. • Locating utilities, electrical circuits • Reduced generator needs during utility work • Evaluating access, connections • Truck access • CDF roof access • etc. etc. etc J. Lewis--CDF Decomminssioning Status

  16. CY2012 CDF Building Improvements on D&D Budget • Main Stairwell • Remove abandoned chilled water pipes • Enclose elevator pump • 2nd floor • Improve exits • Isolate conference rooms and egress paths from assembly area • Collision hall • Sprinklers • Fire doors • Exit lighting J. Lewis--CDF Decomminssioning Status

  17. Plans for Display • Theatre • Place for visitors to assemble • Meet scientist? • Movie? • Trigger room • Electronics on display • Multi-touch table: Exercise in sorting events • Control room • Flashing screens look almost like we are running • Interactive terminals: Middle school shift crews • Stations for SVX, COT, Calorimeter Muons • Mix monitoring plots, etc. for integrated view • Collision hall • North and west sides blown open • Plastic covers, view of COT face, etc. • South and east, closed up in running configuration J. Lewis--CDF Decomminssioning Status

  18. Display Effort • Working with Public Affairs and Education • Making posters to document our achievements • Mix of hardware and physics • Ben Kiliminster coordinating • Interactive activities geared mostly toward middle school • Cosmic-ray test stand, etc. • CDF people: Ben Kilminster, Anna Mazzacane, JDL • Life safety improvements in tour areas • Doors, walkways • Remove obstructions • Remove halon, sprinkler mods J. Lewis--CDF Decomminssioning Status

  19. Planned Collision Hall Layout J. Lewis--CDF Decomminssioning Status

  20. February-March • Configure hall • Open east plug, close SW IMU and S wall, open N wall to max • Harvest components • COT ASDQ boards, TOF PMTs, Diamond BLMs • East Plug Caen crates • Tours • 2/14, 24 – EDIT school • Mezzanine demolition • Stairwell plumbing

  21. April • Assembly pit cleanout • Shelves, cabinets, COT & SVX chillers • 2nd floor construction • Elevator pump enclosure

  22. May • Move sprinkler pipes for IARC door • Cable carrier plumbing and cables(?) • First floor cables(?)

  23. June • Tours 6/11 • Close plug • Open 1200 ton door • Remove N wall, pit steel • Remove Halon squibs

  24. July-August • Remove top and bottom CSP counters • New CH sprinklers • New CH lighting • Other CH construction (doors, etc.) • Return pit steel • Pull NE Arch • Open west plug • Install artifacts on transporter • Tours 8/7?

  25. September • Install N wall • Close shield door • Paint CH floor • Final tour configurations • Plexiglass covers, etc.