1 / 17

Ross Parkman PE Ryan Wester PE

Central Chiller Plant Experience. Ross Parkman PE Ryan Wester PE . Big Ten and Friends Mechanical and Energy Engineering Conference October 1, 2013 . Facilities Operation and Development. Discussion Topics Planning Design Project Delivery and Construction Commissioning and Startup

burt
Download Presentation

Ross Parkman PE Ryan Wester PE

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Central Chiller Plant Experience Ross Parkman PE Ryan Wester PE Big Ten and Friends Mechanical and Energy Engineering Conference October 1, 2013

  2. Facilities Operation and Development • Discussion Topics • Planning • Design • Project Delivery and Construction • Commissioning and Startup • Operations • Q&A

  3. Facilities Operation and Development • Significant Planning Milestones • Feasibility Study Med Center Chiller Plant June 2004 • Campus Infrastructure Master Plan March 2006 • Preliminary Design and Cost Estimate Sept 2006 • Additional Studies and Value Engineering • Redesign option for “Building Loop” • Planning/design New Bed Tower and Existing Hospital HVAC Upgrades • Feasibility Study/Life Cycle Cost for “Building Loop” vs. Central Plant • Plant Site Studies (W of Cannon / 10th Ave, W of Cannon / E of Cannon) • A/E and Construction Manager Contracts Aug 2009 • Program of Requirements Oct 2009 • Estimate of Probable Cost Nov 2009

  4. Facilities Operation and Development • Key Project Dates • Chiller Order (6 @ 2500 tons) June 2010 • Construction Start January 2011 • Initial Equipment Testing May 2012 • “Construction” Chilled Water August 2012 • “Reliable” Chilled Water October 2012 • 2 Additional Chillers December 2013 • Plant Statistics • 20,000 tons initial plant capacity (5000 tons on standby generators) • Awarded LEED Silver by USGBC • 10,000 tons future expansion • Free cooling future addition

  5. Facilities Operation and Development • Design and Project Delivery • Tunnel and distribution piping designed and constructed as part of Med Center Expansion Project • Building Exterior Design by Signature Architect • Local Architect of Record and Engineering Team • Controls integrator on A/E team • Design and building modeling with Revit • Chillers selected and direct purchased through State of Ohio Term Contract • Active input by OSU Utilities (McCracken Chiller Plant Experience) • Commissioning Agent

  6. Facilities Operation and Development • Design and Project Delivery (cont.) • Utilized Construction Reform opportunity: • State of Ohio designated 3 demonstration projects for Construction Reform • Medical Center Expansion including Chiller Plant was identified as the “LARGE” demonstration project • A modified project delivery method was applied utilizing “Design Assist” by the following contracting specialties • Mechanical, Electrical, Structural, Concrete • Design assist contracts established with Guaranteed Maximum Pricing (GMP) • Construction Coordination Model in Navisworks with Construction Manager as lead • Included all equipment, steel and pipe and conduits (>=2 inch diameter) • Resolved all interferences • Produced shop fabrication drawings

  7. Facilities Operation and Development • Design and Project Delivery (cont.) • Distribution Tunnel to new Tower and 5 existing buildings, • Cast in place concrete 10’ x12’ • 42” to 36” welded steel chilled water supply and return pipe • 12” inch seamless steam pipe • 6” 316L stainless steel condensate pipe • Valve vaults and provision for future building connections • Chilled Water Distribution • Direct buried HDPE • Transition from HDPE to welded steel in four valve vaults • Primary/Secondary Pumping with Plate and Frame Heat Ex. • Primary pumps maintain chiller and positive bridge flow • Secondary building pumps maintain flows for building temperature control

  8. Facilities Operation and Development • Project Delivery Method Key Benefits • System designed to match pre-purchased chillers • Design Assist under GMP provided an effective process for equipment evaluation/selection and value engineering • Model review and update meetings insured construction was coordinated and stayed on schedule • Modeling eliminated rework of shop fabricated piping due to interferences • Common commissioning agent for both Plant and Building Systems

  9. 3D BIM Construction Model of #1 Chiller (Navisworks)

  10. Installation of chillers 1 - 6 on second floor of the plant

  11. Facilities Operation and Development • Inspections • Construction • Structural steel and concrete • UT weld examinations: steam, chiller water and condensate piping • Hydrostatic tests • A/E as Contract Administration • Construction Manager • Final Inspections • ODIC • <=480 volt electrical • Building systems • Life Safety • OSU Utilities (as AHJ) • 575V and higher electrical • Instrumentation and control wiring • Process piping and equipment

  12. Facilities Operation and Development • Equipment Readiness • Mechanical • Vendor/Contractor startup support • Pipe flushing with system pumps at 7-9 fps, (chiller tube bundles bypassed) • Frequent startup strainer cleaning • Metal passivation and chemical treatment systems • Electrical • Vendor/Contractor startup support • Phase checks • Relay and wiring checkout • Controls • Field instrument calibration and verification • Point to point zero and span check 134 field devices, one time, complete through to the graphical interface • Verified wiring, communication and graphical displays for 3500 total points • .

  13. Facilities Operation and Development • Site Acceptance Testing (SAT) and Commissioning • Hydraulic flow testing of distribution loop (chiller plant & bldg. pumps) • Systematic test and verification of all Control Sequences • Condenser Pumps, Cooling Towers, Chiller Water Pumps, Chillers • Tested chillers with “warm” loop water prior to building conversions • Go live • Building chillers kept as backup for two weeks • Midnight conversion of first two buildings (8/17/12 and 8/24/12) • Initial testing and controls tuning completed by 7:00 AM • Reliable Chilled Water/Backup Generators • Tested load share with utility • Controlled load assumption • Full Black Start Test • Third building conversion (10/16/12)

  14. Facilities Operation and Development • Operating Results • Med Center reports improved building temperatures and chilled water system reliability • Plant operates on full automatic • Four daily walkthroughs for equipment checks and water quality testing • Towers and chillers stage on and off to satisfy building cooling needs • Metrics • 0.76 kw/ton (central plant only, range 0.72 to 0.78) • 17% (preliminary) net reduction in campus electricity for central chilling • 98% of production metered and billed at buildings • $3800/ton initial build (with standby generation) • $2950/ton final build out (estimated) • Some increase in net building utility costs but with improved service levels

  15. Facilities Operation and Development

  16. Facilities Operation and Development Questions?

  17. Facilities Operation and Development • Thanks to the Project Team!

More Related