An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Portfolioof Biomass Projects in the Czech Republic David Viduna BTG Central Europe s.r.o. San Salvador, March 28, 2003

  2. Background • Favorable conditions • > 20 municipal biomass projects in the Czech Republic were under development • core finance from State Environmental Fund • co-finance was needed Czech Republic

  3. Background II Favorable conditions • BTG’spilot JI projects (AIJ) in several CEE countries • BTG’s municipal biomass pilot JI (AIJ) project in Hostětín, Czech Republic 732 kW biomass boiler in Hostětín

  4. BTG’s JI bundling approach Senter ERUs delivery baseline, proposal & reporting funds bulk contract proposal and transaction approvals BTG Project developer BioHeat Financing intermediary “Bundling Fund” Host country govt. project development & ER monitoring individual contracts 1 2 X .... project portfolio

  5. The Czech Portfolio for ERUPT • >20 municipal central heating systems 0.5 to 10 MW • Biomass (woodchips/straw) replaces individual or central fossil fuel boilers • Project type: fuel switch CO2 em. reduction + avoided methane from waste wood dumps • Emission reduction: up to 240 ktons of CO2e. (ERUs) per year.

  6. The Czech Portfolio for ERUPT

  7. The Czech Portfolio for ERUPT • ERU-PT contract: 0.5 million ERUs for EUR 4.7 million • JI funds linked to the system of the Czech State Environmental Fund (SEF) • SEF support: up to 40% grants and up to 40% zero interest loans • JI funds represent 10 to 20% of the total investment

  8. Status • contract with the Dutch Ministry of Economic Affairs/SENTER • contracts with municipalities • approval from the Czech Ministry of Environment

  9. Summary • Homogeneous bundle • type • size (over a critical value) • owner • baseline • timing

  10. New portfolios/bundles • Bundle/portfolio of 6-7 biomass projects in CEE • Bundle/portfolio of 4 landfill gas projects in CEE