1 / 38

Basin Commision Meeting November 20, 2013 Coeur d’Alene, Idaho EPA and DEQ Team Represented by Bill Adams

Basin Commision Meeting November 20, 2013 Coeur d’Alene, Idaho EPA and DEQ Team Represented by Bill Adams. Summary of 2013 Work . Property remediation – 130 Properties Paved roads in Box and Basin - 8 Miles Remedy protection & unpaved roads Repositories

butch
Download Presentation

Basin Commision Meeting November 20, 2013 Coeur d’Alene, Idaho EPA and DEQ Team Represented by Bill Adams

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Basin Commision MeetingNovember 20, 2013Coeur d’Alene, IdahoEPA and DEQ TeamRepresented by Bill Adams

  2. Summary of 2013 Work • Property remediation – 130 Properties • Paved roads in Box and Basin - 8 Miles • Remedy protection & unpaved roads • Repositories • Lower Burke Canyon – 60% design complete • Ninemile WCA – ready for Interstate Waste in 2014 • CTP and CIA design work at 30% • Lower Basin pilot projects – Selected two projects working on design of one. • Basin Environmental Monitoring Plan (BEMP)

  3. Property Remediation • 130 properties completed • PHD Lead Health Intervention Program outreach • Over 360 children participated in testing this year (92 in Basin and 276 • A total of 15 of those children had blood-lead levels above 5 µg/dl.

  4. Commercial Property Remediation by the Trust • Property Remediation - 2 Parcels • Shoshone county yard – Osburn (approx. 490,00 sq ft) – Out to Bid will start soon • US Silver parking lot – Silverton (approx. 130,00 sq ft) • Work being conducted by Ferguson Construction

  5. Paved Roads Program Smelterville Pinehurst Mullan

  6. Ninemile Cemetery Unpaved Road Project

  7. 2013 REMEDY PROTECTION CONSTRUCTION PROJECTS • Grouse Creek in Smelterville • Sierra Nevada in Wardner completed • Little Pine Creek in Pinehurst 2014 • Third Street Area in Mullan • Dewey Street Area in Mullan • Unnamed Creek in Silverton • Shields Gulch in Osburn2014 (some work started in 2013)

  8. Remedy Protection Projects Completed! Grouse Creek Sierra Nevada Wardner

  9. 3rd St. in Mullan Remedy Protection Project

  10. Repositories • Lower Burke Canyon Design • WCA under construction • Big Creek and EMF in operation

  11. Lower Burke Canyon Repository

  12. LBCR Schedule • Open House to present the 30% design – June 4th Wallace • Few comments on design – response distributed on July 25th • Evaluating several alternatives based on comments and waste volume needs • 60% Basis of Design – August 2013 • 90% Basis of Design – November 2013 • Ongoing groundwater monitoring – throughout 2013 • Construction planned for 2014

  13. LBCR Conceptual View from Woodland Park

  14. Other Repository Alternatives • Expand LBCR to the West • Expand LBCR to the East toward creek and south • Evaluate removal and replacement of SVNRT with increased capacity • Evaluate potential expansion near Big Creek Repository – Site characterization started in Nov 2013.

  15. Potential Big Creek Expansion

  16. East Fork of Ninemile • Most impacted tributary in the Upper Basin- 64 times Water Quality Standards, up to 480 lbs per day of Zinc below Success and High particulate lead to South Fork  • In RODA capping for many sites and was changed to Excavation/local WCA • Why Interstate First • High in Watershed – Top Down Approach • Waste totally fills stream valley • Particulate loader • Close to WCA • Good opportunity for restoration

  17. EFNM Waste Consolidation Area • Design for 1.3M cy of mine waste for all of Ninemile Basin • Potential expansion for 2.0M cy • Phased development • Initial development in 2013 allows for placement of mine waste from I-C Rock Dumps in 2014 • WCA development has provided soil, woody material, and rock for construction of WCA, infrastructure, and reconstruction/restoration of remedial sites

  18. WCA

  19. BEMP Update • EPA is planning to conduct an optimization of GW monitoring on OU2 and all other BEMP data • FWS collecting pre-RA data in EFNM and Canyon Creek • Ongoing evaluation of all data for lessons learned, trends, opportunities to streamline data collection

  20. Lower Basin Pilot Projects • Pilot Projects Selected and moving forward! • With lots of help from locals – 46 ideas received from 24 individuals/entities • Focusing on 2 projects at this time • A combined Riverbank and Beach Remediation Kahnderosa Campground • Water Level Management Using Hydraulic Controls at location TBD

  21. Riverbank & Beach Remediation at Kahnderosa Campground • Objectives: • Reduce potential exposure to people from contaminated material in banks and beaches • Isolate contaminated material beneath clean and stable soil • Support recreational use & ecological habitat • Measure recontamination • Measure and document stability

  22. Water Level Management • Objectives • Use clean tributary flows to maintain higher water levels • Deter Waterfowl Use During Migration Season • Reduce contamination deposition during high flows • Monitor Waterfowl Usage and Feeding Patterns, Water Levels, Sediment Deposition Rates and Related Factors

  23. Pilot Projects – Next Steps • EPA working with landowners and eco resource folks will select and commence planning for the pilot projects • Construction for both is planned for 2014 • Will Post Update to the EPA Website on These Projects

  24. Lower Basin Sampling • Focused Data Gathering to Better Define the Sub-bottom • Focused Coring in the Floodplain to Update Depositional Rates/Concentrations

  25. CTP Upgrades and CIA Groundwater Collection

  26. Design Concept Optimization and Modeling • Reduce contaminant loading to surface water • Minimize infiltration of surface water into the GCS • Minimize overall groundwater collection flow rates • Minimize O&M requirements (system maintenance and fouling) • Maximize hydraulic isolation of the CIA and extent of hydraulic capture • Maximize system flexibility

  27. Extraction Well/Cutoff Wall • 8,800-foot-long cutoff wall • Series of 10 extraction wells • Flow rate is more prescribed by wells at ~2,000 gpm • Flow from SFCDR and lower confining layer isolated from wells by cutoff wall

  28. Remedy Effectiveness • No-action dissolved zinc loading to SFCDR estimated to be ~540 lb/day • Zinc loading under eastern OU 2 ~ 450 lb/day • Zinc loading moving through groundwater system toward Smelterville Flats ~ 90 lb/day • Estimated effectiveness 65-90% reduction • Range depends on concentration entering SFCDR after installation of slurry wall.

  29. Budget Update • Current Special Account Balance ~ $52 million w/out Hecla’s last payments • Trust Balance ~ $504M (end of 3rd quarter) up $22M in last quarter. • HQ funding this year $2M

  30. Planned Trust Budget for 2014 • Approximate Trust Budget - ~ $21 million • Remedy Protection in Box and Basin • WCA and Interstate construction • Pre-design data collection - Ninemile • Property Remediation construction • Roads construction ($3.5M in Basin) • Lower Basin Pilots construction • Repository Operations • LBCR construction

  31. Planned Special Account Project Work for 2014 – Budget TBD • Ongoing Property Remediation • Remedy Protection in Box • Paved Roads Program in Box ($3.5M) • Lower Basin data collection/modeling • Oversight , Admin, and Supporting Activities • BEMP • CTP and CIA design completion

  32. Summary of Hecla Settlement Funds (from 8/12 presentation)

  33. Status ofHecla Funds • Amount of Settlement ~ $180M • Amount received to date ~$138M ($66M + $72M) • Amount in Court Registry ~$66M • Amount in Special Account $52M • Due in 2014 balance up to $42MWork completed to date from SA (includes other settlment funds) • Property Remediation • Technical Support and RD • Support Agency Agreements • Paved Roads in Box

  34. Special Account Funding Challenges • Total Funds Available = $52M + $42M • Key project commitments in Box that can’t be funded by Trust = $67M • Completion of CTP and GW Collection over 3 years -$36M (placed on contract in Jan 2015) • Remedy Protection - $4M • Roads - $27M over 6 years • Balance of $27M for other site needs

  35. Misc Updates • Community Fill Plan • Implementation Plan Update – advertized via email, Basin Bulletin, facebook, placed in library – 30 day informal review

  36. Thank You

More Related