An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fall Water users meeting November 9, 2016

  2. Windy Gap Project • Built 1985; 1 reservoir, 1 pumping plant and pipeline • Makes use of “unused capacity” in the C-BT Project • Reliable annual yield: ZERO • Junior water right, lack of storage • Original plan called for terminal storage by individual participants

  3. 13 participating providers

  4. Preferred Alternative –Chimney Hollow Reservoir Carter Lake Reservoir Chimney Hollow Reservoir Flatiron Reservoir

  5. Chimney Hollow • 90,000-AF capacity • 740surface acres • Use established Colorado River rights • Tie into C-BT • ~30,000 AF firm yield • $400 Million

  6. Chimney Hollow Partnership • 3,400 acres owned by Hewlett-Packard as future employee recreation site • Purchased in partnership between Larimer County (1800 ac as open space) and NCWCD (1600 ac as future reservoir site) in 2004.

  7. Chimney Hollow Partnership • IGA in place for site planning/development and future management that stipulates: • Lease to Larimer County to manage future reservoir recreation; • Day-use only; • Water quality assurances • Non-motorized boating (except small electric motors); • Joint development of property mgmt plan • Joint development of future access • Current management activities include forest stewardship, weed management, guided public tours. • Management Plan – future public access.

  8. Current Status Milestones Completed: Remaining Milestones: • Draft EIS (August 2008) • Biological Opinion for ESA Compliance (Feb 2010) • Colorado Fish and Wildlife Mitigation Plan (June 2011) • Colorado Fish and Wildlife Enhancement Plan (June 2011) • Final EIS (November 2011) • Fish and Wildlife Coordination Report (March 2012) • 1041 Permit from Grand County (Dec 2012), includes: • IGA with Grand County • Windy Gap Reservoir Bypass Funding Agreement • Learning By Doing Agreement • Grand Lake Clarity MOU with Grand County (June 2012) – still needs Reclamation approval • Reclamation: • Conveyance Contract • Record of Decision • Corps of Engineers: • CDPHE 401 certification • Corps of Engineers 404 Permit • Permits Anticipated in 2016 • Design Begins July 2016 • Power Line Relocation: 2017 • Begin Construction:2018? Future Chimney Hollow Reservoir

  9. Windy Gap Bypass – aka “Connectivity Channel”

  10. Connectivity Channel

  11. Drill Rig setup

  12. Drill cores

  13. Test Pit excavation

  14. Logging test pit

  15. Other Ongoing Tasks • WAPA power line relocation design • Mitigation planning and design – nutrient removal • Cultural Resource Studies • Property Acquisition • Financing Plan

  16. Remaining milestones • Army Corps of Engineers: 404 permit to build • Anticipated dates • Permit completion: early 2017 • Design: 2016-2018 • Construction: 2018-2021 • Project Cost - $400M