260 likes | 393 Views
. KY Background. Medicaid is the primary payer source for health care in KentuckyCovers nearly half of all births in the Commonwealth per yearProvides health coverage to 1 out of every 3 children, and 1 out of every 7 seniors over age 65Provides coverage to approximately 740,000 enrollees, repres
E N D
1. 2009 NAMPI Conference
CMS Systems Certification: Kentuckys Recent Experience
2. KY Background
3. KY Background 39,955 enrolled providers (as of 3/24/09)
FY09 Budget = $5.54 billion
FY10 Budget = $5.7 billion (projected)
4. Certification Background MMIS Certification Modernization
5. Certification Background Process unchanged for the past 25 years
Begins 6 + months after commencement of operations
MMIS defined as claims processing engine and 6+ subsystems
Basis of Review--State Medicaid Manual (SMM) Part 11 requirements
Reviewers rely on checklists covering 6 - 8 subsystems
6. Medicaid Enterprise Certification Toolkit
7. Certification Review Transformation
8. Tools in the Toolkit
9. Old Checklist Format
10. Sample New Checklist
11. 20 New Certification checklists
12. SDLC and the Toolkit
13. Certification Overview
14. KY Procurement Lifecycle
15. KY MMIS Project Timeline
16. KY Certification Approach
17. Coordination of Effort
18. KY Documentation Points
19. KY Site Visit Logistics
20. KY Program Integrity Preparation Review the MITA assessment
Verify the requirements related to PI
Review the Implementation APD
Verify the requirements have been met
Review the RFP and proposal
Verify the requirements related to PI
Certification Toolkit
Verify the requirements related to PI
21. KY Program Integrity Preparation Assigned reviewers (two) to verify the checklist documentation
An SME and a person not as familiar with PI
Checked each answer on the checklist/protocol
Does it adequately answer the question?
Did we attach enough documentation?
Does it illustrate functionality from Go-Live? Etc.
22. KY Program Integrity Preparation Reviewer walkthrough of the system
Reviewers performed a functional walkthrough of the system
Does the system function according to the documentation provided?
Do the screen prints match the system?
Do all of the reports work correctly? Etc.
Does the system match the APD, MITA assessment, RFP etc? (this should only be a cursory check at this point in the process)
23. KY Program Integrity Preparation Prepared Staff
Assigned an interviewer
Performed mock interviews with staff
Job function
Processes used
Describe reports used
Demonstrate use of the system
Select random reports to generate
Ensured staff understood the checklist
Reassured staff
Prepared Business Partners
24. Other Items Review the last PI Audit (ensure any deficiencies have been addressed)
Address defects (a large number of defects could indicate issues)
Change orders (a large number of outstanding change orders could indicate issues)
TPL Action Plan (up-to-date?)
Suspended/Denied Claims (higher than before?)
Reporting (who, what, when, where)
MSIS Files (up-to-date?)
25. CMS Certification