MICE Absorber and Test Cryostat Shigeru Ishimoto KEK MICE AFC Module Phone Conference (March 12, 2004) (1) MICE Absorber Test Process (2) MICE Absorber Latest Drawing (3) MICE Absorber Test Cryostat (Plan)
MICE Absorber Test Process 3-5 Bodies (KEK) 6-10 Windows (USA) G-He Test at 20K (KEK) Test & MICE Experiment at RAL L-H2 Test at MTA with a Spear Body and Windows
Detail Test Process US/FNAL (3) Pressure Test at R.T. KEK (1) Pressure Test at R.T. with Dummy Windows (2) Pressure Test by G-He at 20 K with Dummy Windows KEK (or FNAL) (4) Pressure Test at R.T. with Windows (5) Pressure Test by G-He at 20K with Windows (2)&(5) Needs Test Cryostat (A) Test Cryostat at MTA L-H2 Test (B) New Horizontal Test Cryostat Cold G-He Test RAL (6) Pressure Test at R.T. (7) Cooling Test by G-He (8) Cooling Test by L-H2
MICE Absorber (Latest Drawing)
L-H2 Level Sensor Stay Off Lines
MICE Absorber Test Cryostat (Plan)
MICE Absorber Test Cryostat (Plan)
MICE Absorber Test • Horizontal test cryostat will be design and fabricate at KEK. • It will be used at KEK by cold G-He at 10-20K. • Cold test at 10-20K with real windows • Ship to RAL with real windows (ready to use) • L-H2 test at FNAL/MTA by a spear MICE absorber