TEP 10 YR PLAN (2009 – 2018)

TEP 10 YR PLAN (2009 – 2018). WestConnect Planning Workshop Phoenix, Arizona November 13, 2008 Ron Belval Tucson Electric Power, Inc. SATS Participants & Stakeholders “Single System Planning Principle”. Transmission Providers APS, SWTC, TEP, Western PNM, EPE Transmission Customers

chaeli
Download Presentation

TEP 10 YR PLAN (2009 – 2018)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TEP 10 YR PLAN(2009 – 2018) WestConnect Planning Workshop Phoenix, Arizona November 13, 2008 Ron Belval Tucson Electric Power, Inc.

  2. SATS Participants & Stakeholders“Single System Planning Principle” • Transmission Providers • APS, SWTC, TEP, Western • PNM, EPE • Transmission Customers • CAP, Ft. Huachuca, SSVEC, Trico • Project Developers • Acciona, Bowie, Entegra, SunZia • Regulators • ACC • Other Interested Parties • APA, AzISA, EPG, NM RETA, WSES

  3. Open Stakeholder Process • Local Jurisdictions • Potential Future Substation Sites and Transmission Corridors Reflect Local Jurisdictions’ Existing Land Use Plans • Regional Coordination • SWAT, WestConnect and TEPPC • Stakeholder Involvement per FERC Order 890 • SWTC and TEP Joint Meetings • June 5, 2008 & December 9, 2008

  4. Inter-Subgroup Coordination Modeled Mega-Projects with “Scenario” Generators • 2009 Study Plan reflects • Impact of flow through • NM → AZ → Western Markets • Renewable Energy Projects • Capture over lapping boundary opportunities • CATS → SATS • SPPR Three Terminal Proposal

  5. SATS EHV & 230kV 10 Year Projects Refer to Projects – 10 Year Plan Slides

  6. Note A: Joint project. Participants are considering deferral to 2013. Note B: Joint project. TEP evaluating feasibility of deferral to 2013.

  7. Note A: Bicknell transformer relocated to Greenlee. Note B: Joint project. Deferral possible due to competing alternative project(s).

  8. Note A: Deferral possible due to competing alternative projects. Note B: Under evaluation.

  9. Note A: Joint project. To be included in future SWTC capital work plan. Note B; 1st 230kV line identified in the SATS study needing upgrade. Note C: 2nd 230kV line identified in the SATS study needing upgrade.

  10. Note A: Investigation on going in Cochise County Study plan for 2009. Note B: Substation related to Kartchner – SC2 – San Rafael project.

  11. Note A: Structure upgrades to raise conductor operating temperature to 150˚C. Note B: Rconductor scheduled for 2016.

  12. Note A: New line associated with new Cienega substation. Note B: Project and schedule are subject to revision. Note C: Schedule is subject to revision. 1st phase of plan to reconductor 3 circuits on triple circuit structures.

  13. Note A: Project and schedule are subject to revision. To coordinate with new Kino substation. Note B: Relocation from WESTERN’s Nogales 115kV switching station to the TEP Vail 345/138kV substation. Includes segment of new 138kV plus 115kV line and substation upgrades to 1138kV. Note C: 2nd phase of plan to reconductor 3 circuits on triple circuit structures. Note D: 3rd phase of plan to reconductor 3 circuits on triple circuit structures.

  14. Note A: Project and schedule are subject to revision.

  15. TEP 10 Year Plan to be Revised • TEP Load Forecast to be Updated • Reflecting lower growth considering current economic conditions • 10 Year Plan to be submitted to ACC in January 2009 will be revised • Anticipate significant changes from WestConnect submittal