HBD Commissioning (II)

HBD Commissioning (II). Progress from October 3 to November 28, 2006. Itzhak Tserruya HBD group meeting November 28, 2006. Pre-beam commissioning (I). October 3: cooldown starts on Dec. 1 st and that we will not see collisions before Jan. 1 st , 2007.

channer
Download Presentation

HBD Commissioning (II)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD Commissioning (II) Progress from October 3 to November 28, 2006 Itzhak Tserruya HBD group meeting November 28, 2006

  2. Pre-beam commissioning (I) • October 3: cooldown starts on Dec. 1st and that we will not see collisions before Jan. 1st, 2007. • Present situation: cooldown starts on Jan 2nd and we will not see collisions before Feb. 1st. • Pre-beam commissioning status: • done • in progress • to be done • the two detectors installed • all cables (signal, HV and LV) connected • Gas recirculation system operational • Gas monitoring system – Bob/Craig • UV lamp monitoring -- Sasha/Tom/Craig • readout electronics operational & take data in stand-alone mode – Chi • HV software fully operational – Deepali/Takao

  3. Pre-beam commissioning (II) • noise optimized • dead channel count • pedestal runs done routinely • timing and data taking with pulser done routinely • data taking with UV-lamp – Sasha/Tom/Craig • ADC charge calibration for all detector modules • first order zero suppression -- Maxim • Monte Carlo simulations • basic Geometry and materials in • reconstruction up to the pad response • 3d map in +- configuration • cluster reconstruction • tracking to HBD

  4. Pre-beam commissioning (III) • HBD online monitoring, including: • Event display: pad response • Event display: cluster response • Pulse height distribution of a detector modules • Pad frequency vs. pad number • Cluster size distribution • Cluster pulse distribution • Tracking in the +- field • 3d field map Very good progress over the last two months in spite of QM and we still have about 2 months to complete this program. I think it is doable in this amount of time.