This presentation discusses the commissioning process for the CM-2 cryomodule, which is a Type 3+ ILC type Cryomodule with 8 cavities. The process includes cold commissioning, setting up motor temperature, tuning to resonance, and on-resonance conditioning. The presentation also mentions the milestones achieved so far and the application of the cryomodule to LCLS-II.

Download Presentation

CM-2 Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CM-2 Commissioning Elvin Harms LCLS-II Weekly Meeting 12 March 2014

  2. Introduction • CM-2 is • Type 3+ ILC type Cryomodule • 8 cavities (1.3 GHz) built by industry • Vertical and Horizontal tests at Fermilab & JLab (good to 35 MV/m) • Cryomodule assembled at Fermilab • first ILC type cryomodule which may reach average gradient specification of 31.5 MV/m • Designed for pulsed operation • Main accelerating device for ASTA • Expect beam tests in FY2015

  3. Commissioning Process • Prerequisites • cryomodule installed • pipes welded and certified leak tight • pressure tests successful • vacuum circuits leak tight (beam tube, coupler, insulating vacuum) • any necessary warm conditioning completed • cooldown • Single cavity powering • Power all cavities together, characterize system performance • Follow-on studies E. Harms APT Seminar 14 January 2014

  4. Commissioning Process E. Harms APT Seminar 14 January 2014

  5. Cold Commissioning – Single Cavity • Tune cavity to resonance • Map out and set QL • System calibrations, calculate gradient, k • On-resonance conditioning • Determine peak performance • Final (high power) LLRF calibration • Lorentz Force Detuning Compensation set-up • Document dark current, x-rays vs. gradient • Dynamic Heat Load measurements (Q0) E. Harms APT Seminar 14 January 2014

  6. Setting Up Motor temperature Df ~ 240 MHz Motor steps Goal 1.30 GHz Start here Tuning to Resonance E. Harms APT Seminar 14 January 2014

  7. Setting Up Setting QL 3-3.5 E6 E. Harms APT Seminar 14 January 2014

  8. Cold Commissioning – On-resonance conditioning Conditioning Sequencer • 20 ms to 1.3 ms pulse width • 1-2 Hz repetition rate • Peak power 1 MW (narrow pulse width) or < 25 MV/m • Monitor • Vacuum • Field Emission (3 points) • PMT • Coupler window temperatures • Automated process (mostly) Cavity #4 Conditioning E. Harms APT Seminar 14 January 2014

  9. Lorentz Force Detuning Off On E. Harms APT Seminar 14 January 2014

  10. Peak Gradient 27 February 2014: CM-2 Cavity 3 achieves 31.5 MV/m (Administrative limit) 5 Hz, 1.6 ms pulse width, LFDC Active E. Harms APT Seminar 14 January 2014

  11. Dark Current/X-rays Threshold ≥ 20 MV/m E. Harms APT Seminar 14 January 2014

  12. Performance to Date ILC Milestone CM2 installed at ASTA

  13. Timeline • Cryomodule installed in NML/ASTA – April 2013, • Warm coupler conditioning (one cavity at a time) – 9 May to 18 June 2013 • Cooldown – 23 October to 11 November 2013 • Begin cold operation, Cavity 1 only – 13 November 2013 • Cavity 1 complete (13 November - 30 January) • Cavity 2 complete ( 31 January - 15 February, 16 days) • Cavity 3 complete ( 24 February – 4 March, 9 days) • Cavity 4 complete ( 4 – 10 March, 6 days) • Cavity 5 begin next week (beam line installation access this week) • Cavity 6 • Cavity 7 • Cavity 8 E. Harms APT Seminar 14 January 2014

  14. Application to LCLS-II Cryomodules • Some facets of commissioning are more pertinent to pulsed/high peak power operation • coupler conditioning (necessary?) • peak gradient • Q0/DHL measurement critical • Good to start with single cavity testing, but necessary as experience gained? • CM2 a good check on component performance/reliability • Visitors welcome to come and observe/participate • Follow-on ideas welcome

  15. Summary • CM2 cold commissioning since December • Half of the Cavities are now characterized • Pace is picking up, estimate ~2 weeks/cavity • Performance as hoped for so far • Full cryomodule testing in May? • Open to visitors and additional studies

  16. Thanks