Facilities Modernization Program Funded by Measure B Project Report. March 19, 2012. PROJECT PROGRESS REPORT PE Phase III (Outside Loop Road). LAS POSITAS COLLEGE March 19, 2012. Project Team: Architect : WLC Architects / Carducci Landscape Architects
E N D
Facilities Modernization Program Funded by Measure B Project Report March 19, 2012
PROJECT PROGRESS REPORT PE Phase III (Outside Loop Road) LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Architect: WLC Architects / Carducci Landscape Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Lathrop Construction Project Update: • Project is complete. • DSA Closeout is in progress. • Occupancy: 04/2011
PROJECT PROGRESS REPORT Science Building, Phase II LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Architect: Kwan Hemni • Construction Manager: Parsons Brinckerhoff • Contractor: Broward Builders, Inc • Project Update: • Interior Casework, Lighting and Fume hoods being installed. • Exterior Painting is in progress. Interior Painting is Completed. • Electrical and Data installation and termination is continuing at first and second floors. • Flooring at 2nd floor classrooms completed. • Storefront installation and Glazing Completed. • Stair Treads installed. Occupancy: 09/2012
PROJECT PROGRESS REPORT Student Services & Central Administration LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Architect: Steinberg Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Zovich Construction • Project Update: • GFRC installation complete. • Storefront installation has started along with glazing. • Site fine grading is complete. • Building metal panels have to start within 2 weeks. • Sheetrock has started on one side of the walls. • Elevator installation to begin next week. • Roofing is complete. Occupancy: Spring 2013
PROJECT PROGRESS REPORT Campus Boulevard Phase I-III LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Architect: Gates & Associates • Construction Manager: Parsons Brinckerhoff • Contractor: TBD Project Update: • 100% Design review completed, final design was Approved by DSA February 2012. • Project was Bid on March 13, 2012 and Low Bid Contractor will be Board Approved April 17, 2012 • Design Re-Start: 04/2011 • DSA Permit Approval: 02/2012 • Construction Start: 05/2012 Occupancy: TBD
PROJECT PROGRESS REPORT Photovoltaic System Phase II LAS POSITAS COLLEGE March 19, 2012 • Project Team: • Design Build Contractor: Cupertino Electric Inc. • Construction Manager: Parsons Brinckerhoff Project Update: • Fencing Completed. • Racking System and Array installation is completed. • Inverters and Transformer installed and completed. • New Switchgear tie in during Spring Break. Operational: February 2012