1 / 4

Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization Program Funded by Measure B Project Report. December 17, 2012. PROJECT PROGRESS REPORT Student Services & Central Administration. LAS POSITAS COLLEGE December 17, 2012. Project Team: Architect : Steinberg Architects

taji
Download Presentation

Facilities Modernization Program Funded by Measure B Project Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities Modernization Program Funded by Measure B Project Report December 17, 2012

  2. PROJECT PROGRESS REPORT Student Services & Central Administration LAS POSITAS COLLEGE December 17, 2012 • Project Team: • Architect: Steinberg Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Zovich Construction • Project Update: • Ceiling tile is being installed on the 2nd floor. 85% complete. • Tile in the entry corridor is complete and has started in the gallery. • Interior trim is 95% complete. Kitchen Equipment is 90% installed. • Ceilings grid in the dining areas is complete, wood slats to follow within the next 2 weeks. • Site concrete is 95% complete. Irrigation and planting are complete. Paver installation is complete. Landscape maintenance period has started. Occupancy: Spring 2013

  3. PROJECT PROGRESS REPORT Campus Boulevard Phase I-III LAS POSITAS COLLEGE December 17, 2012 • Project Team: • Architect: Gates & Associates • Construction Manager: Parsons Brinckerhoff • Contractor: Suarez & Munoz Construction, Inc. Project Update: • Concrete Pathways 100% Complete, with parts of the pathways open. Library and Grand Stairs Complete • Underground Electrical and Lighting are 100% Complete • Boulders for the wet fountain have been placed, with the dry art area completed and are open to students and faculty • Underground mainlines and laterals are 100% completed. • Grading work is 90% completed with planting continuing with completion to be 12/29/12 • Occupancy: 12/31/12

  4. PROJECT PROGRESS REPORT Science Building, Phase II LAS POSITAS COLLEGE December 17, 2012 • Project Team: • Architect: Kwan Hemni • Construction Manager: Parsons Brinckerhoff • Contractor: Broward Builders, Inc • Project Update: • New Science Bldg 1850 Complete, Punch List work is 95% complete and in progress • Bldg 1800 Remodel Complete, Punch List work is 95% complete and in progress • Closeout is in progress Occupancy: 09/2012

More Related