1 / 6

Facilities Modernization Program Funded by Measure B Project Report

Facilities Modernization Program Funded by Measure B Project Report. September 16, 2013. PROJECT PROGRESS REPORT Library Remodel. LAS POSITAS COLLEGE September 16, 2013. Project Team: Architect : Noll & Tam Construction Manager : Parsons Brinckerhoff Contractor : TBD

pete
Download Presentation

Facilities Modernization Program Funded by Measure B Project Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Facilities Modernization Program Funded by Measure B Project Report September 16, 2013

  2. PROJECT PROGRESS REPORT Library Remodel LAS POSITAS COLLEGE September 16, 2013 • Project Team: • Architect: Noll & Tam • Construction Manager: Parsons Brinckerhoff • Contractor: TBD Project Update: • Architect selection completed in May with Board approval in June • Project is in final design development phase with cost estimates provided to users • Submission for DSA review scheduled for November 20, 2013 • Occupancy: December 2014

  3. PROJECT PROGRESS REPORT Renovations – 100, 900, 1000, 1310/1320, 1700 LAS POSITAS COLLEGE September 16, 2013 • Project Team: • Architect: Charles Ham and Associates • Construction Manager: Parsons Brinckerhoff • Contractor: TBD Project Update: • .Conceptual design meetings have started for B1700–Print Shop, Mail Room and Large Group Meeting Room • Conceptual design meeting are scheduled for B1310/1320- Veterans Program • B100 on Hold, B900 –classroom in service • B1000 will be demolished once vacant • B700– Swing space for Library during B2000 renovation • Occupancy: Phased

  4. PROJECT PROGRESS REPORT Student Services & Central Administration LAS POSITAS COLLEGE September 16, 2013 • Project Team: • Architect: Steinberg Architects • Construction Manager: Parsons Brinckerhoff • Contractor: Zovich Construction • Project Update: • Substantial Completion was issued March 6, 2013. • Punch Lists are complete. • .The building is fully occupied • Closeout is in progress. Occupancy: March 15, 2013

  5. PROJECT PROGRESS REPORT Science Building, Phase II LAS POSITAS COLLEGE September 16, 2013 • Project Team: • Architect: Kwan Hemni • Construction Manager: Parsons Brinckerhoff • Contractor: Broward Builders, Inc • Project Update: • New Science Bldg 1850 Complete, Punch List complete. • Bldg 1800 Remodel Complete, Punch List complete. • 1 year warranty period is complete • Closeout for DSA is in progress. Occupancy: 09/2012

More Related