Project X Working Group Meeting

Project X Working Group Meeting. January 15, 2008 2:00 PM Snake Pit. Agenda. Planning for ICD Cost Review DOE 413.3A Requirement Office of Science Approval Matrix Requirement Temple Conversation with Lehman Holmes Conversations with Procario Director’s ICD Cost Review

chynna
Download Presentation

Project X Working Group Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project X Working Group Meeting January 15, 2008 2:00 PM Snake Pit

  2. Agenda • Planning for ICD Cost Review • DOE 413.3A Requirement • Office of Science Approval Matrix Requirement • Temple Conversation with Lehman • Holmes Conversations with Procario • Director’s ICD Cost Review • Draft Charge [Temple and All] • Draft Committee [Temple and All] • Quick walkthrough of CD-0 Prerequisites for Project X [Temple] • Resource and Schedule Forecast • Project X’s CD-0 Prep Status [Kerby, McCluskey] • Discussion on Additional Review Preparations [Holmes and All] • Possible Schedule for the ICD Cost Review • If time permits - Project Timeline [Dean and All] • Next Meeting – Third Thursdays [Dean] • Status of Action Items 15-Jan-09 Project X WGM

  3. DOE O 413.3Actions Authorized by Critical Decision Approvals 15-Jan-09 Project X WGM

  4. 15-Jan-09 Project X WGM

  5. Lehman Comments on CD-0 IPR - 1 • “That’s a technical review.” • For OHEP would probably reference HEPAP priorities and excerpt something from a HEPAP report. That’s what was done for NSLS-II. They did NOT HAVE a separate Mission Need IPR. 15-Jan-09 Project X WGM

  6. Lehman Comments on CD-0 IPR - 2 • Lehman talked with Procario early in the new year • Said had shared these comments with Mike • And noted that they could do a “Technical Review” if that is what is desired by OHEP • Temple relayed this input to Holmes who said he’d follow-up with Procario 15-Jan-09 Project X WGM

  7. Draft Charge 15-Jan-09 Project X WGM

  8. Tentative Committee 15-Jan-09 Project X WGM

  9. Quick Walkthrough • The following is a quick walkthrough of CD-0 Requirements for Project X mostly slanted to near term actions to prepare for Director’s Cost Review of the Initial Configuration Document. • I’ve highlighted slides that were shown and discussed in the September 25 Project X WGM Meeting. 15-Jan-09 Project X WGM

  10. CD-0 Prerequisites for Project X • Perform Pre-conceptual Planning activities that focus on the Program’s strategic goals and objectives, safety planning, and design. • Prepare a Mission Need Statement that documents a mission requirement that cannot be met through other than material means. Additionally, the Mission Need Statement will document the potential hazards and their safety, security, and risk implications. • DOE G 413.3-17 Mission Need Statement Guide http://www.directives.doe.gov/pdfs/doe/doetext/neword/413/g4133-17.pdf • Mission Need Statement Review. The Office of Program Analysis and Evaluation within the Office of the Chief Financial Officer will review the Mission Need Statement and provide a recommendation to the Program Secretarial Officer • Perform Mission Validation Independent Project Review (Lehman Review). A Mission Validation Independent Project Review is a limited review prior to CD-0 for Major System projects. It validates the mission need and the cost range. A Value Study may also be conducted, as appropriate, to assist in CD-0. 15-Jan-09 Project X WGM

  11. Other Pre CD-0 Work • Develop estimate to request Project Engineering and Design (PED) funds. PED funds are requested at CD-0 using a Project Data Sheet as “design only” funds for preliminary and final design. PED funds are not to be used for construction, long-lead procurement, or major equipment items. PED funding requests are developed from historical data or parametric estimates. • The objectives for the use of PED funds are to: • Improve the accuracy of the project cost estimate and support establishment of the Performance Baseline • Improve the DOE’s planning, programming, and budgeting process for the acquisition of projects • Provide funds for Value Management (VM) activities • PED funds can be made available at CD-1 15-Jan-09 Project X WGM

  12. Approach • Planned Approach - describe what has been considered or what will be analyzed as potential strategies • Assumptions • Constraints • Technical Risks • Safety Risks • Cost Risks • Schedule Risks • Legal Risks Identify these risks as input to OHEP as they write the MNS Develop Cost Risks for Cost Review 15-Jan-09 Project X WGM

  13. Resource and Schedule Forecast • Rough Order of Magnitude Cost Estimate Range - (-50 percent to +100 percent, for example) of project cost and schedule based on the upper bound of the rough order of magnitude estimate. • Estimated Cost - resource planning funding profile with a breakout of project engineering and design funds and an explanation of funding needs to proceed from Critical Decision-0 to Critical Decision-1. • Rough Order of Magnitude Schedule Estimate - identify the estimated dates (fiscal year only) for meeting subsequent Critical Decisions 15-Jan-09 Project X WGM

  14. Project X CD-0 Prep Status • See Presentation by Jim Kerby and Elaine McCluskey 15-Jan-09 Project X WGM

  15. Possible Schedule for the ICD Cost Review • Initial Thoughts • Week of Feb 16 • Week of Mar 16 15-Jan-09 Project X WGM

  16. Timelines • If there’s time, I’d like to get an update of current thinking about these possibilities. • Nearly 3 months have gone by since the September 25 WGM. • Do we know enough to say one of these is more real than the other? 15-Jan-09 Project X WGM

  17. Timeline Scenarios • Construction Start FY13; PED FY11 • Construction Start FY14; PED FY12 • Assumes: April deadline for CD-0 approval and one budget cycle (18 months) for PED funds availability Construction start = CD-3b approval and one budget cycle (15-18 months) after CD-2 15-Jan-09 Project X WGM

  18. Case #1TimelineCD-0 Spring 09, PED funds FY11 15-Jan-09 Project X WGM

  19. Case #2TimelineCD-0 Fall 09, PED funds FY12 15-Jan-09 Project X WGM

  20. Next Meeting • Recurring WGM to be Monthly • Third Thursday of each month from 2:00 PM - 4:00 PM in the Snake Pit (WH2NE) 15-Jan-09 Project X WGM

  21. Action Items 15-Jan-09 Project X WGM