An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 12 Enterprise Resource Planning MRP Video Lecture (MRP A)

  2. MRP • Computerized inventory control & production planning system • Schedules component items when they are needed - no earlier and no later • 2

  3. When to Use MRP • Dependent and discrete items • Complex products • Job shop production • Assemble-to-order environments • 3

  4. Material Requirements Planning Product Structure File Inventory Master File MRP Inputs & Outputs Master Production Schedule Planned Order Releases Rescheduling Notices Work Orders Purchase Orders • 4

  5. MRP Inputs • Master production schedule • Product structure file • Inventory master file • 5

  6. Master Production Schedule • Drives MRP process with a schedule of finished products • Quantities represent production not demand • Quantities may consist of a combination of customer orders & demand forecasts • Quantities represent what needs to be produced, not what can be produced • 6

  7. Master Production Schedule • 7

  8. Board (1) Pressboard (1) Finish (2oz.) Product Structure Tree Clipboard Level 0 Clip Assembly(10) Rivet (2) Level 1 Top Clip (1) Bottom Clip (1) Pivot (1) Spring (1) Level 2 Sheet Metal (8 in2) Sheet Metal (8 in2) Spring Steel (10 in.) Iron Rod (3 in.) Level 3 • 8

  9. Indented Bill of Material LEVEL ITEM Unit of Measure Quantity 0 - - - - Clipboard Ea 1 - 1 - - - Clip Assembly Ea 1 - - 2 - - Top Clip Ea 1 - - - 3 - Sheet Metal In2 8 - - 2 - - Bottom Clip Ea 1 - - - 3 - Sheet Metal In2 8 - - 2 - - Pivot Ea 1 - - - 3 - Iron Rod In 3 - - 2 - - Spring Ea 1 - - - 3 - Spring Steel In 10 - 1 - - - Rivet Ea 2 - 1 - - - Board Ea 1 - - 2 - - Press Board Ea 1 - - 2 - - Finish Oz 2 • 9

  10. Specialized BOMS • Phantom bills • transient subassemblies • never stocked • immediately consumed in next stage • K-bills • group small, loose parts under pseudo item # • reduces paperwork • 10

  11. Specialized BOMS • Modular bills • product assembled from major subassemblies & customer options • modular bill kept for each major subassembly • simplifies forecasting & planning • X10 Automobile example 3 x 8 x 3 x 8 x 4 = 2,304 configurations 3 + 8 + 3 + 8 + 4 = 26 modular bills • 11

  12. Modular Bill Of Material X10 Automobile Engines Exterior Interior Interior Body (1 of 3) Color (1 of 8) (1 of 3) Color (1 of 8) (1 of 4) 4-Cylinder (.40) Bright Red (.10) Leather (.20) Grey (.10) Sports Coupe (.20) 6-Cylinder (.50) White Linen (.10) Tweed (.40) Light Blue (.10) Two-Door (.20) 8-Cylinder (.10) Sulphur Yellow (.10) Plush (.40) Rose (.10) Four-Door (.30) Neon Orange (.10) Off-white (.20) Station Wagon (.30) Metallic Blue (.10) Cool Green (.10) Emerald Green (.10) Black (.20) Jet Black (.20) Brown (.10) Champagne (.20) B/W Checked (.10) • 12

  13. Inventory Master File Description Inventory Policy Item Board Lead time 2 Item no. 7341 Annual demand 5,000 Item type Manuf. Holding cost 1 Product/sales class Ass’y Ordering/setup cost 50 Value class B Safety stock 25 Buyer/planner RSR Reorder point 39 Vendor/drawing 07142 EOQ 316 Phantom code N Minimum order qty 100 Unit price/cost 1.25 Maximum order qty 500 Pegging Y Multiple order qty 100 LLC 3 Policy code 3 • 13

  14. Inventory Master File, Con’t. Physical Inventory Usage/Sales On hand 100 YTD usage/sales 1,100 Location W142 MTD usage/sales 75 On order 50 YTD receipts 1,200 Allocated 75 MTD receipts 0 Cycle 3 Last receipt 8/25 Difference -2 Last issue 10/5 Codes Cost acct. 00754 Routing 00326 Engr 07142 • 14

  15. Inventory Accuracy 1. Maintain orderly stockrooms 2. Control access to stockrooms 3. Establish & enforce procedures for inventory withdrawal 4. Ensure prompt and accurate entry of inventory transactions 5. Take physical inventory count on a regular basis 6. Reconcile inventory discrepancies in a timely manner (use cycle counting) • 15

  16. The MRP Matrix • Item • name or number identifying scheduled item • LLC • low-level-code; lowest level at which item appears in a product structure • 16

  17. Parts Of MRP Matrix • Lot size • order multiples of this qty; can be min/max qty • LT (lead time) • time from order placement to receipt • PD (past-due) • orders behind schedule • Gross requirements • demand for item by time period • 17

  18. Scheduled receipts • quantity already on order & receipt date • released orders become scheduled receipts • Projected on hand • expected on-hand inventory at end of period • Net requirements • net amount needed after on-hand adjustments • Planned order receipts • net requirements adjusted for lot-sizing • Planned order releases • planned order receipts offset by lead time • 18

  19. MRP: Problem 1 • A company produces two products: Product A and Product Q. The owner has received an order from a customer of 103 units of product A for week 8 and 200 units of product Q for week 7. The product structures and other pertinent information are given below in the table as well as on top of each MRP table. Develop a materials requirements plan that will provide the customer the two products. • 19

  20. MRP: Problem 1 • 20

  21. Product Structure Item A • 21

  22. Product Structure Item Q • 22

  23. MRP: Problem 1 - Solution • 23

  24. MRP: Problem 1 – Solution (cont.) • 24

  25. MRP: Problem 1 – Solution (cont.) • 25

  26. MRP: Problem 1 – Solution (cont.) • 26

  27. MRP: Problem 1 – Solution (cont.) • 27

  28. MRP: Problem 1 – Solution (cont.) • 28

  29. MRP: Problem 1 – Solution (cont.) • 29

  30. MRP: Problem 1 – Solution (cont.) • 30

  31. MRP: Problem 1 – Solution (cont.) • 31

  32. MRP: Problem 1 – Solution (cont.) • 32

  33. MRP: Problem 1 – Solution (cont.) • 33

  34. MRP: Problem 1 – Solution (cont.) • 34

  35. MRP: Problem 1 – Solution (cont.) • 35

  36. MRP: Problem 1 – Solution (cont.) • 36

  37. MRP: Problem 1 – Solution (cont.) • 37

  38. MRP: Problem 1 – Solution (cont.) • 38

  39. MRP: Problem 1 – Solution (cont.) • 39

  40. MRP: Problem 1 – Solution (cont.) • 40

  41. MRP: Problem 1 – Solution (cont.) • 41

  42. MRP: Problem 1 – Solution (cont.) • 42

  43. MRP: Problem 1 – Solution (cont.) • 43

  44. MRP: Problem 1 – Solution (cont.) • 44

  45. MRP: Problem 1 – Solution (cont.) • 45

  46. MRP: Problem 1 – Solution (cont.) • 46

  47. Chapter 12 Enterprise Resource Planning MRP Video Lecture (MRP B)

  48. Planned Order Report Item #2740 Date 9-25-02 On hand 100 Lead Time 2 weeks On order 200 Lot size 200 Allocated 50 Safety Stock 50 Order No. Gross Reqs. Scheduled Receipts Projected On Hand Date Action 50 9-26 AL 4416 25 25 9-30 AL 4174 25 0 10-01 GR 6470 50 -50 10-08 SR 7542 200 150 Expedite SR 10-1 10-10 CO 4471 75 75 10-15 GR 6471 50 25 10-23 GR 6471 25 0 10-27 GR 6473 50 -50 Release PO 10-13 Key: AL = allocated CO = customer order PO = purchase order WO = work order SR = scheduled receipt GR = gross requirements • 47

  49. MRP Action Report Current date: 9-25-02 Item Date Order No. Qty. Action #2740 10-08 7542 200 Expedite SR 10-1 #3616 10-09 Move forward PO 10-7 #2412 10-10 Move forward PO 10-5 #3427 10-15 Move backward PO 10-25 #2516 10-20 7648 100 De-expedite SR 10-30 #2740 10-27 200 Release PO 10-13 #3666 10-31 50 Release WO 10-24 • 48

  50. Capacity Requirements Planning (CRP) • Computerized system that projects load from material plan • Creates load profile • Identifies underloads and overloads • 49