Status of Readout Boards and Gas Monitoring System. Craig Woody BNL. Upgrade Working Group June 6, 2006. Readout Boards. Instrumentation cannot meet production schedule to deliver all readout boards by mid July Have located two outside vendors who can produce boards in
E N D
Status of Readout Boards and Gas Monitoring System Craig Woody BNL Upgrade Working Group June 6, 2006
Readout Boards • Instrumentation cannot meet production schedule to deliver all readout boards by mid July • Have located two outside vendors who can produce boards in 10 days after receipt of artwork. Price is ~$900/board from one company, $500/board from the other. First company has material in stock, other company does not. • Prototype for LSH full scale board will be finished in Instrumentation shop by end of this week • RHS full scale design will be finished by end of this week • If prototype board is ok, will proceed with production at outside vendor for delivery by end of June • Board stuffing will also be done by outside vendor. All parts in hand. 5 day turnaround C.Woody, HBD Working Group Meeting, 6/6/06
Gas Monitoring System • Almost complete at McPherson. Delivery scheduled in two weeks • All other purchased components in hand • Need to manufacture few parts here at BNL (gas cells, phototube holders, etc). • Should be no problem to complete by mid July. C.Woody, HBD Working Group Meeting, 6/6/06