1 / 15

SOFIA Program Status Bob Meyer January 10, 2010 Program Manager

SOFIA Program Status Bob Meyer January 10, 2010 Program Manager. Agenda. Executive Summary Recent and Upcoming Events Program Status Schedule (Bar chart and Lego chart) Risks Concerns / Issues Program Summary. Executive Summary. Program has made significant progress

cjared
Download Presentation

SOFIA Program Status Bob Meyer January 10, 2010 Program Manager

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SOFIA Program Status Bob Meyer January 10, 2010 Program Manager

  2. Agenda • Executive Summary • Recent and Upcoming Events • Program Status • Schedule (Bar chart and Lego chart) • Risks • Concerns / Issues • Program Summary

  3. Executive Summary • Program has made significant progress • Cavity Door Drive System (CDDS) final flight test controller and software installed and working • Mission Control & Communication System (MCCS) open door software and hardware checked and working • Cavity Environmental Control System (CECS) experiencing failures, but is repaired and working • Provides drying and some heating to cavity prior to and during descent • 100% door open flight accomplished December 18th • Science preparation on track for first science (instruments, labs, etc) • Other status • JSPP II signed • Agreement on German workforce for operations • German Science Data archiving agreement is TBD • Segment 3 planning underway • FIFI lost funding • Limited slack to ISF milestone • Program and Center’s working recovery strategies

  4. Door Full Open Flight, Dec 18, 2009

  5. Recent and Upcoming Events • AFSRB part 2 at DAOF; November 19, 2009 • Combined Systems Test; November 16-20, 2009 • Mission Readiness Brief at HQ; November 30, 2009 • SSPC at DSI in Stuttgart, Germany; December 3-4, 2009 • Functional Check Flight; December 4, 2009 • 10% Door Open Flight; December 11, 2009 • 100% Door Open Flight; December 17, 2009 • American Astronomical Society Meeting in Washington D.C.; January 3-7, 2010 • SOFIA Splinter Session; January 4, 2010 • SRB; Late-March 2010 • DPMC; Mid-April 2010 • APMC; Late-April 2010 • TA Characterization/First light; spring 2010 • Instrument workshop, June 2010, Asilomar, CA • First science; fall 2010

  6. Schedule Overview (Bar Represents Tracking Schedule and red triangles represent our commitment) We are here! Instrument Commissioning Inst 1 Inst 2 Inst 3 Inst 4 Inst 5 First in-flight Light Inst 6 Door open Flight Arrival at Dryden First Door closed flight Backup HIPO Line Ops TA V&V Basic Science SS D-Check FIFI-LS Downtime CY07 CY08 CY09 CY10 CY11 CY12 CY13 CY14 3 0 1 2 4 FOC LOC ISF Avionics Upgrade Cavity Insulation Segment 3 Downtime Elements CECS Upgrade ISF = Initiation of Science Flights LOC = Limited Operational Capability FOC = Full Operational Capability SS = Short Science MCCS Upgrade Observatory Upgrades Science Flight activity Imager Improvements Engineering & Inst. Comm Flight activity A/C Testing/Work

  7. Segment 2 – Tracking dates TA Misalignment (daytime) TA Activation 2010 TA Characterization/First Light attempt TA Characterization ISF IMS:SOFIA_IMS100112Araw.mpp Created 1/12/2010

  8. Segment 2 – Tracking dates 2011 IMS:SOFIA_IMS100112Araw.mpp Created 1/12/2010

  9. Segment 3 – Tracking 2012 LOC 2012 2013 2013 FOC 2014 2014 IMS:SOFIA_IMS100112Araw.mpp Created 1/12/2010

  10. Program Key Milestones

  11. Program Risk Management Matrix L x C Trend Decreasing (Improving) Increasing (Worsening) Unchanged New Since Last Period Approach M - Mitigate W - Watch A - Accept R - Research Criticality  High p [Risks are identified and trended from last review to current review] Med   Low

  12. SOFIA Program Risk Waterfall * RAC as averaged over the 12 open Program Risks * Segment 3 SRR Mitigations Open Door V&V/FCF/Open Door Flight Mitigations

  13. Program Summary Program has made significant progress Achieved 100% door open flight on December 18th Program successfully implemented recovery plan to achieve FCF and 100% door open flight prior to end of calendar year On-track to ship FORCAST soon Integration and line ops late winter TA characterization (door open and TA unlocked) and first light expected early April. Program has a concern with limited slack to Initiation of Science (ISF) Working recovery options

  14. Back-up

  15. CURRENT PLAN, per FRR slides

More Related