An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPSNeutrino Facility Preliminary Proton Forecast Rende Steerenberg with help from K. Cornelis, S. Cettour-Cave, B. Goddard. SBLNF meeting

  2. Content • Assumed super cycle configurations • Preliminary proton forecast based on time sharing • Primary Protons Beam Power • Summary SBLNF meeting

  3. Combined FT – NF Super Cycle • Like todays super cycles FT – NF (Presently CNGS) • 1 FT cycle of 15.6 sec. • 4 or 5 cycles of 3.6 sec. in 6 sec. slots. • 3.6 sec. NF cycles in 6 sec. slots for PS Complex physics users. • ISOLDE ratio day/night: 38% / 37%. • Combined FT – NF operation is not possible, as ZS needs to be retracted. • Super cycle used for comparison reasons. • NF would receive 3.76 x 1019 protons per run. SBLNF meeting

  4. Time Sharing Super Cycles for FT • Day time: • 2 FT cycles of 10.8 sec. • 2 MD cycles of 7.2 sec. • 2 ZERO cycles of 1.2 sec. • Max. rms current for SPS main circuits • Night time: • 2 FT cycles of 10.8 sec. • 6 ZERO cycles of 1.2 each • Max. rms current for SPS main circuits SBLNF meeting

  5. Time Sharing Super Cycles for NF • Day time: • 5 NF cycles of 3.6 sec. in 6 sec. slots. • 1 MD cycles of 7.2 sec. • Night time: • 6 NF cycles of 3.6 sec. in 6 sec. slots. SBLNF meeting

  6. Proton Forecast With Time Sharing • Run assumptions: • 3.5 x 1013 protons per SPS pulse (Presently limited by PS extraction flux and radiation dose rate) • Transverse emittances compatible with extraction (remains to be confirmed) • Physics run of 200 days shared between FT and NF. • 75% accumulated SPS beam availability. • No FT and NF physics during LHC filling (on average about 4 hours per 24 hours). • If NF would run at 60% then FT receives same number of protons as today. • 2.85 x 1019 protons per run (50% would results in 2.37 x 1019 protons per run). • If NF would run at 75% then FT received same number of pulses as today. • 3.56 x 1019 protons per run. • However, • Many different NA users, today’s schedule is ful,l Is 50% - 60% NF realistic with shorter runs ? • Experimental switching to be synchronized with NA off periods. SBLNF meeting

  7. ICARUS-NESSIE request vs. delivery potential • Protons request1): • 4.5 x 1019 protons in 1 year for neutrino mode. • 9 x 1019 protons in 2 years for anti-neutrino mode. • 1.35 x 1020 protons in total in 3 years. • Resulting in 4.5 x 1019p.o.t. per year. • Potential proton delivery: • ~ 2.85 x 1019 protons per years (60% time for NF). • Approximate duration is 4.7 runs of 200 days. 1) Taken from the ICARUS-NESSIE contribution to the European Strategy for Particle Physics. SBLNF meeting

  8. Beam Power Estimates • Normal running 100 GeV: • 3.5x1013ppp every 6 sec. • Beam energy 100 GeV • Beam power: 95kW (during NF run period) • Ultimate running 120 GeV: • 4.5x1013ppp every 3.6 sec. • Beam energy 120 GeV • Beam power: 240 kW (during NF run period) • Ultimate running 100 GeV: • 4.5x1013ppp every 3.6 sec. • Beam energy 100 GeV • Beam power: 200 kW (during NF run period) SBLNF meeting

  9. Summary / Conclusion • Combined running not possible, unless considerable structural changes to SPS lattice are made. • ZS (NA electrostatic slow extraction septum) to be retracted during NF runs. • 3.6 sec. NF cycle in 6 sec. time slot required for PS complex physics. • Realistic time sharing: • 50% - 60% for NF  2.85 x 1019 p/yr. • Equal or slightly more pulses and protons for NA • Shorter runs per test beam and synchronized experimental switching required. • Make careful choices to allocate experiments to SPS-NA orPS-EA. • About weekly based time sharing is probably most efficient and equally shares down time. • Nominal NF Beam Power ~ 95 kW (mainly limited by PS extraction). • NF design should be based on the ultimate beam power of 240 kW at 120 GeV, or 200 kW if we decide to stay at (or below) 100 GeV. • Required amount of protons could be delivered in 4.7 runs of 200 days each. • Final extraction scheme, transverse emittances and beam losses remain to be confirmed to consolidate the present preliminary estimate. SBLNF meeting

More Related