Gwynneth Davidoff, Kendall Pletcher, Mary Schmidt, Amy Whitcombe MXS controljune18, 2010
Timeline update from Keith • LED, 10kV DC-DC converter will be sent tomorrow • No readily available vacuum pump system at Olin, so it will take a week to send the MXS (with MCA and source) • This moves MXS testing back a few days, giving us more time for lab testing/ making improvements • See chart at http://nasa.ece.olin.edu/projects/2010/mxs/files/PERT_chart.xlsx
Coding progress • GUI: • Reorganized code • Looking at Brad’s code • PIC: • Took out unnecessary portions of Brad’s code
Next steps • Continue finalizing GUI and PIC code • Work on interfacing GUI and PIC • Test circuits for current, temperature measurement