Objective FCM03. ESSIP Plan 2013. Octavian CIOARA DSS/EIPR 13.09.2013. Objective FCM03. Comprehensive Explanation What is new or has changed since LSSIP 2012 Link to European ATM Master Plan Most important SLoA(s) Finalisation Criteria and Closed Questions ESSIP Report 2012
E N D
Objective FCM03 ESSIP Plan 2013 Octavian CIOARA DSS/EIPR 13.09.2013
Objective FCM03 • Comprehensive Explanation • What is new or has changed since LSSIP 2012 • Link to European ATM Master Plan • Most important SLoA(s) • Finalisation Criteria and Closed Questions • ESSIP Report 2012 • Objective Coordinator’s Analysis, recommendations, tips & tricks • Links and contacts ESSIP Plan 2013 / Objective FCM03
Comprehensive Explanation • This ECAC wide objective aims at: • Improving the collaboration between the NM, ANS providers, airports and airspace users in filing and distributing flight plans, • Assist airspace users in filing their flight plans and in re-routings according to the airspace availability and ATFM situation. • Improve flight plan distribution to increase consistency of flight plan data amongst all parties involved (IFPS/ETFMS, ANS Providers). ESSIP Plan 2013 / Overview LSSIP 2012
What is new or has changed since LSSIP 2012 • Emphasis on the automation of the generation of the AFP message (SLoAs ASP05, ASP06, ASP07, ASP13, ASP14) • In case of manual generation of these messages, the “completed’ status of these SLoAs has to be changed. • Full operational capability (FOC) date changed from 12/2012 to 12/2015 • Finalisation dates of ASP05 to ASP11 and ASP13 to ASP14 changed to 12/2015 • Changes triggered by the Interim Deployment Programme (IDP) ESSIP Plan 2013 / Overview LSSIP 2012
Link to European ATM Master Plan • OI Step [DCB-0302] - Collaborative Management of Flight Updates • OI Step [IS-0101] - Improved Flight Plan Consistency Pre-Departure • OI Step [IS-0102] - Improved Management of Flight Plan After Departure ESSIP Plan 2013 / Overview LSSIP 2012
Most important SLoA(s) • ASP04 Processing of APL and ACH messages, • ASP05 Automatically provide AFP for Missing flight plans, • ASP06Automatically provide AFP message for Change of route, • ASP07Automatically provide AFP message for a Diversion, • ASP09 Provide AFP message for a Change of requested cruising level. • Each SLoA should be fulfilled in accordance with the relevant provisions of the CFMU Flight Progress Messages document ESSIP Plan 2013 / Overview LSSIP 2012
Finalisation Criteria and Closed Questions • Automatic processing of: • Flight plan messages in ICAO format • FPLs derived from RPLs • ATC system able to receive and process flight plan data from IFPS in ADEXP format • Processing of APL and ACH messages • Automatic generation and provision to NM of the AFP messages in ADEXP format for: • Missing flight plans • Route changes • Diversions • Changes of aircraft type • Changes of aircraft equipment ESSIP Plan 2013 / Overview LSSIP 2012
ESSIP Report 2012 • Objective late, with a slight improvement in its implementation since the previous reporting period. The States yet to implement the most essential SLoAs of this objective have shown a sound commitment to do so. However, the likelihood of implementing all SLoAs still remains low. • The implementation of the objective involves a certain level of investments; it is done through the planned upgrades of current ATM systems or the installation of the new ones. At the same time stakeholders do not recognise direct benefit from implementation. • The implementation is not progressing as expected resulting in: • An inefficient use of the available Network capacity • Late provision of flight plan updates to ATC ESSIP Plan 2013 / Overview LSSIP 2012
Objective Coordinator’s Analysis, recommendations, tips & tricks • Implement the most important SLoA(s) • Pay attention to the need for automation of the AFP message • Amend the progress status if necessary • For partial completion of the objective be more specific on what has been completed and the prospects for the rest of the SLoAs. • Ensure that there is an effective link with the NM and the information on the implementation originates from a ODSG member. ESSIP Plan 2013 / Overview LSSIP 2012
Links and contacts Objective Coordinator: Octavian Cioara +32 2 729 3282 octavian.cioara@eurocontrol.int NMD Objective Expert: J. Koolen +32 2 729 9876 johannes.koolen@eurocontrol.int ESSIP Plan 2013 / Overview LSSIP 2012