1 / 5

PARCA Timeline

PARCA Timeline. Transmission Workgroup 4 th July 2013 Rhys Ashman. Previous Timeline Shared with Industry. Draft Workgroup Report. Ofgem decision on Mod. Final Workgroup Report. Panel decision on Mod. Panel decision on Consultation. Consultation Period.

crwys
Download Presentation

PARCA Timeline

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PARCA Timeline Transmission Workgroup 4th July 2013 Rhys Ashman

  2. Previous Timeline Shared with Industry Draft Workgroup Report Ofgem decision on Mod Final Workgroup Report Panel decision on Mod Panel decision on Consultation Consultation Period This was a very high level timeline It did not include updates to, and consultation of, Methodology Statements and the Generic Revenue Driver Methodology It also did not include the 56 day period of appeal of proposed Licence changes Licence Change Consultation Period NG NTS & Ofgem undertake Licence Drafting Ofgem Direct Changes to Licence

  3. Draft Revised Timeline for discussion Customer Seminar Draft Workgroup Report Ofgem decision on Mod Final Workgroup Report Panel decision on Mod Panel decision on Consultation Consultation Period Licence Change Consultation Period NG NTS & Ofgem undertake Licence Drafting Ofgem Direct Changes to Licence 56 day period of appeal of proposed Licence changes Methodology Statements Consultation Period NG NTS request Ofgem consent for a derogation on Licence condition for independent examination of methodology statement changes Ofgem period of approval NG NTS consider responses & make necessary updates NG NTS request Ofgem consent for a derogation on Licence conditionfor independent examination of Generic Revenue Driver Methodology changes Generic Revenue Driver Methodology Statement Consultation Period NG NTS consider responses & make necessary updates Ofgem period of approval

  4. Draft Revised Timeline Comments Extended period for Ofgem decision on Mod as falls over Christmas period Customer Seminar Licence and Methodology Statement Consultations undertaken together following mod decision Draft Workgroup Report Ofgem decision on Mod Final Workgroup Report Panel decision on Mod Panel decision on Consultation Consultation Period Licence Drafting to be completed before Christmas Licence Change Consultation Period NG NTS & Ofgem undertake Licence Drafting Ofgem Direct Changes to Licence 56 day period of appeal of proposed Licence changes Methodology Statements Consultation Period NG NTS request Ofgem consent for a derogation on Licence condition for independent examination of methodology statement changes Ofgem period of approval NG NTS consider responses & make necessary updates If independent examinations are required, this is likely to extend the timescales for approval of Methodology Statements and GRDM NG NTS request Ofgem consent for a derogation on Licence condition for independent examination of Generic Revenue Driver Methodology changes Generic Revenue Driver Methodology Statement Consultation Period NG NTS consider responses & make necessary updates Ofgem period of approval

  5. Implications of Changes • Draft Workgroup Report to be submitted one month later (now September) • This results in Ofgem’s Mod decision being communicated in January rather than December (extended timescales included to account for Christmas period) • Licence Drafting has been removed from the critical path but has been replaced by the 56 day period of appeal of licence changes • The Licence and Methodology Statement Consultations occur in parallel following Mod Approval • The Implementation of Mod, Licence changes, revised Methodology Statements, revised GRDM & revised Charging Statement to be at the end of April, rather than at the start.