1 / 6

PROJECT PROGRESS REPORT Project : Project name Prepared by : Your name Date: DD-MM-YYYY

PROJECT STATUS :. Go-Live. Progress. PROJECT PROGRESS REPORT Project : Project name Prepared by : Your name Date: DD-MM-YYYY. Highlights Workload Consumption Workload consumption planned(md)- Workload consumption actual(md) - Estimation To Complete (md) - Progress follow-up

curry
Download Presentation

PROJECT PROGRESS REPORT Project : Project name Prepared by : Your name Date: DD-MM-YYYY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROJECT STATUS: Go-Live Progress PROJECT PROGRESS REPORTProject: Project namePrepared by: Your nameDate: DD-MM-YYYY Highlights • Workload Consumption • Workload consumption planned(md)- • Workload consumption actual(md) - • Estimation To Complete (md) - • Progress follow-up • Coverage (%) - • Success Status(%) - Next Steps • Your text • Your text • Your text • Your text Difficulties and risks • Risk for Go-live date • Your text • Your text • Your text Defects and Issues Follow-up • New found defects • Resolved defects • Closed defects Legend: On schedule Small delay Big delay Blocked

  2. PROJECT STATUS DASHBOARD On Schedule Medium High Go-Live Risk! ! +25% High Risk! -100% +100% Lowest Highest Actual Vs Planned Go-Live Risk PROJECT TASKS DISTRIBUTION 2140 2000 60 50 20 10 PASSED FAILED IN PROGRESS NOT STARTED ABANDONED TOTAL REMAINING WORKLOAD: E F 80% PROJECT PROGRESS TILL DD-MM-YYYY 10 20 30 40 50 60 70 80 90 100 PROJECT Kick-Off PROJECT Sign-Off 0 40% 50% PLANNED ACTUAL

  3. PROJECT STATUS DASHBOARD On Schedule Medium High Go-Live Risk! ! +25% High Risk! -100% +100% Lowest Highest Actual Vs Planned Go-Live Risk PROJECT TASKS DISTRIBUTION 2140 2000 60 50 20 10 PASSED FAILED IN PROGRESS NOT STARTED ABANDONED TOTAL REMAINING WORKLOAD: E F 80% PROJECT PROGRESS TILL DD-MM-YYYY 10 20 30 40 50 60 70 80 90 100 PROJECT Kick-Off PROJECT Sign-Off 0 40% 50% PLANNED ACTUAL

  4. PROJECT STATUS DASHBOARD On Schedule Medium High Go-Live Risk! ! +25% High Risk! -100% +100% Lowest Highest Actual Vs Planned Go-Live Risk PROJECT TASKS DISTRIBUTION 2140 2000 60 50 20 10 PASSED FAILED IN PROGRESS NOT STARTED ABANDONED TOTAL REMAINING WORKLOAD: E F 80% UAT PROGRESS TILL NOW (23-05-2013) 10 20 30 40 50 60 70 80 90 100 PROJECT Kick-Off PROJECT Sign-Off 0 40% 50% PLANNED ACTUAL

  5. PROJECT STATUS DASHBOARD On Schedule Medium High Go-Live Risk! ! +25% High Risk! -100% +100% Lowest Highest Actual Vs Planned Go-Live Risk PROJECT TASKS DISTRIBUTION 2140 2000 60 50 20 10 PASSED FAILED IN PROGRESS NOT STARTED ABANDONED TOTAL REMAINING WORKLOAD: E F 80% PROJECT PROGRESS TILL DD-MM-YYYY 10 20 30 40 50 60 70 80 90 100 PROJECT Kick-Off PROJECT Sign-Off 0 40% 50% PLANNED ACTUAL

  6. Calculations of bar sizes and angles • Actual vs. Planned dash angle calculation • 0’ is the angle where the dash is exactly in the middle, which means the project goes straight on schedule. • In case the project progress goes behind or forward the schedule the angle is calculated as a percentage of 90’ • Example: If the project goes 20% faster than planned – then the dash should be moved 20%*90’ = 18’ • Go-Live risk • It is not exactly calculated, you can decide where to put the dash, depending on the risk. If it is high – the dash points to the right side • Project tasks distribution • Total bar size 14.8 • Every other bar is calculated as a percentage of 14.8 • Project progress • Total bar size is 12.3 • Every bar is calculated as a percentage of 12.3 • Remaining workload • 0’ is the angle where the dash points into the maximum level of workload • 180’ is the angle where the dash points into the lowest level of workload remaining

More Related