1 / 16

CFAC Review

CFAC Review. Steve Sawch Asst. Director, Construction Management NSLS-II CF Construction Preparations May 8, 2008. Construction Preparations Outline . Construction Delivery Development Construction Delivery Approach Establish BNL Management Team Staffing Requirements

curt
Download Presentation

CFAC Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CFAC Review Steve Sawch Asst. Director, Construction Management NSLS-II CF Construction Preparations May 8, 2008

  2. Construction Preparations Outline • Construction Delivery Development • Construction Delivery Approach • Establish BNL Management Team • Staffing Requirements • CF Organization Chart • Responsibility Matrix • Construction Readiness • Path Forward

  3. Construction Delivery Development • Original Plan • Award to General Contractor • Manage with CM as Agent • Pre-Construction (Liro/Gilbane) • Construction (separate award) • DOE Review Questions • Need to build up BNL staff • What is bid climate • Need to define CM role • CM not at risk – how to motivate CM

  4. Construction Delivery Development • BNL Construction Delivery Review • Analysis of Delivery Methods • CM at Risk (GMP/Multiple Primes) • Agency CM • Lump Sum award to GC • Contractor Outreach • Construction Readiness Workshop • Recommend CM at Risk or BNL to Manage • Decision -BNL to Manage GC

  5. Construction Delivery Approach • Decided to continue with GC construction delivery approach using BNL CF Team as CM • Appears to be qualified competitive pool of contractors for GC bid • BNL CF Team has experience in acting as CM • This approach provides most direct control of contractor performance • CM/GC would introduce new schedule and cost risk for procurement

  6. Establish BNL Construction Team • Team Roles and Responsibilities • Identify Staffing Requirements • Hire Project Team • Permanent • Term • Augment with CM/Engineer Firm staff if needed • BNL Holds Job Fair • Great response from construction and engineering candidates • Team Hires • 3 Engineers Hired • Interviewing candidatesfor construction positions

  7. Construction Staffing Requirements

  8. Conventional Facilities Organization ECS Design Supervisor J. Mills [M] Sr Mech. Engr. C. Channing [M] Project Architect T. McEvaddy [M] Civil/Struct. Engr A.Raphael [M] M. Toscano Sr. Energy Manager Elect. Engineer D. Danseglio [M] [M] – Matrixed [C] - Contracted Conventional Facilities Director M. Fallier Asst. Director CF Design Management O. Dyling Asst. Director CF Construction Management S. Sawch Construction Management Field Team Design Phase CM LiRo/Gilbane N. Heyman [C] Facility Dynamic Modeling & Analysis N. Simos [M] NSLS II Design A/E HDR A. Soueid[C] Civil/Structural Lead Engineer T. Joos Construction Engineer Commissioning Contractor TBD [C] Subconsultants Vita-tech Colin -Gordon VJ Assoc.[C] Lead Electrical Engineer T. Nehring Project EVMS& Schedule P. Selgrad [M] Civil/Arch Inspector Lead Mechanical Engineer J. Gosman Mechanical Inspector Project Cost Accounting C. Retundi [M] Field Office Admin. Asst. Chilled Water Fac. Design A/E Giffels B. Harrison [C] Electrical Inspector CF Procurment Sr Administrator D. Paveglio [M] Construction Safety Specialists [M] 1.5 PE Trade Shop Support – Various [M] CF Procurment Administrator TBD[M]2 CF Admin. Asst.

  9. Construction Readiness • Site Logistics Plan • Site Access Plan • Access Training • BNL PE assisting with site preparation planning and removal of excess facilities • BNL ESH confirmation of environmental status of site • CF Assisting Plan Development • Construction Safety Plan (ESH) • Construction Quality Assurance Plan (PC)

  10. Site Logistics Plan

  11. Existing Site Bldg 100 Bldg 210 Bldg 211 Demolished 2/08 Bldg 87 Bldg 481 Ring Bldg Footprint Construction Area Perimeter Existing Buildings to be removed prior to construction

  12. Site Access Plan • Current Plan • Use Main Gate • Most Efficient • Existing Security • No Cost • Fall Back Plan (Only if Necessary) • Use of South Entrance • Additional Security • Further from Site • Additional Cost

  13. Access Training • BNL Requirements • Construction Safety Orientation • Security Identification • Issue Badges • Screening for Foreign Nationals • Additional Projects • ISB – Interdisciplinary Science Building • BGRR – Brookhaven Graphite Research Reactor • JPSI – Joint Photon Science Institute

  14. Access Training • Could Exceed Current Processing Capacity • Existing on-site location requires escort to training office – inconvenient & time consuming • Working with BNL on Two Approaches • Local Off-site Store Front • Contract out Training & Issuing Badges • Create Onsite Trailer Near Main Gate • Possibly Lab funded or jointly funded by multiple projects

  15. Path Forward • Work with Procurement Team in contractor outreach to secure competitive qualified pool • Continue hiring construction team staff • Develop procedures and management systems • Get them trained on all requirements and ready to start • Finalize construction contract requirements • Finalize development of Construction Management Plan and related documents • Evaluate and implement Construction Document-Control software (Expedition or similar)

More Related