An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CFAC Review Marty Fallier NSLS-IIConventional Facilities Schedule Review December 13, 2006

  2. Schedule • Schedule for conventional facilities developed at detailed level for conceptual design • Needed to develop confidence in schedule phasing and sequencing • Needed to identify key interface points with accelerator & beamline installation • Prepared based on input and discussions with: • LIRO CM scheduling group • Major national CM firm (Gilbane) • Large local contractor (EW Howell) • Consensus that logic, sequencing, phasing and durations are reasonable

  3. Schedule cont’d • Key schedule objective – Enable start of accelerator installation as early as possible • CF is critical path until the main bldg spaces are turned over for accelerator installation • Schedule is reviewed weekly with Project Ctrls, XFD & ASD groups as part of Schedule Task Force Mtgs • Key dependencies: • 1st pentant ready for accelerator installation • Control room ready for installation • BO of Ring Bldg for beamline installation

  4. Schedule Modifications Underway • Recent funding profile guidance differs from the basis used for CDR schedule development • Currently iterating different schedule scenarios based on revised funding profile • Trying to minimize impact to overall schedule • Trying to minimize cost impact due to stretch-out • Evaluating which activities can be deferred with least impact • We are not quite there yet but hope to have confidence in revised schedule impacts in mid-May

  5. CF Schedule (CDR funding profile) FY07 FY08 FY09 FY010 FY11 FY12 Activity FY13 Title I Design CD-2 Title II Design CD-3 Site Prep. Const. (reduced) Pre-cast Shield Wall Const. Ring Bldg Bid & Award 1st Pentant RFE (Pentant 1) 2nd Pentant RFE (Pentant 5) 3rd Pentant RFE (Pentant 2) 4th Pentant RFE (Pentant 3) 5th Pentant RFE (Pentant 4) BLOC & 3 LOB’s CHW Plant Expansion Mech & Elect Utilities Integrated Ctrl & Comm. Standard Equipment Commissioning No LLP Begin Accelerator Installation Full Ring Bldg Available for Accelerator Installation Control Room RFE LOB’s Complete BO for all CF Construction

  6. Integrated Summary Schedule (Constrained Profile)

  7. Detail Schedule Sample

  8. Schedule - Design • Design Activity duration • Title I Design – 8 months (ACD + T-I duration) • Title II Design – 11 months • Not a generous length but is reasonable given the following: • Title I A/E is the CDR A/E – they have a running start • Substantial portion of Title II design is a duplication effort • Pentant 1 &5 (BLOC/LINAC/RF) are unique design-will take focused effort! • Pentants 2, 3 & 4 are nearly identical – design one right and duplicate • Chilled water expansion is duplication of existing CCWF Phase I design • Early confirmation and configuration management of technical design parameters affecting CF is key! • Interface managers have been designated to assure this is done • Accelerator lattice design frozen May 2nd

  9. Schedule - Construction • Construction Activities (CDR Funding Profile) • Site Preparation early procurement– 6 months • Main bldg contract bid & award – 6 months • Main bldg contract duration - 39 months • Chilled Water Plant Expansion – 24 months • Electrical Utilities – 18 months • Mechanical Utilities – 17 months • LN2 system – 9 months

  10. Schedule – Construction cont’d • Analysis – Hi level view (in FY06 $) • At NSLS II site ~$120M in work over ~40 mos = $3M/mo • At CFN $2.4M/mo but in 50ksf building footprint • Footprint for NSLS II is ~300ksf – 6 times the space! • As long as sequencing is correct, there is ample time to get this work done • The space available and layout enables great flexibility in sequencing work so all trades are continuously productive • APS Comparison – (escalated to 06 $) • APS cost $260M over 63 mo = $4.1M/mo vs $3M/mo for NSLS II • APS- 960ksf/63mo = 15ksf/mo vs 361ksf/40mo = 9ksf/mo NSLS II

  11. Schedule Summary • Current schedule provides confidence that scope can be done in scheduled time • Critical path is identified • Critical dependencies & Milestone List are identified • Schedule risk areas identified and mitigation underway (LLP) • Path Forward – Additional schedule development underway: • Analysis of impacts due to funding profile changes • Early assessment is 3-6 month impact but must verify • Weekly Schedule Task Force meetings to maintain up-to-date dependency status and work toward optimization • Will solicit input in schedule development from CM as part of constructability review